Updated April 8, 2024

April targets:

  • Procurement, fabrication, and installation of steel roof trusses
  • Procurement of steel roof sheets, window and door frames
  • Fixing door and window frames
  • Plastering
  • Setting out storm water and foul drainage structures
  • Setting out of ablution blocks and clocktower

Pictures of ongoing construction work can be seen below.

Administration Block

Ready for roofing

Multipurpose Hall

Finalizing rebar fixing (slab to be cast tomorrow)

Classrooms (2No)

Finalizing after beam blockwork

Pavillions (2 No)

Ring beam formwork and rebar preparations

Laboratory (1 No)

Finalizing after ring beam blockwork

Library

Fixing of ring beam formwork

Staff Housing (3 No)

After beam blockwork continues

Hostels (2 No)

Ring beam formwork and rebar fixing continues

Headmaster and Teachers' Housing

Ring beam casting done; blockwork continues

Cafeteria

Blockwork continues

Other Works

1. Block Moulding
245,000 blocks

2. Electrical and plumbing first phase activities in progress

3. Site general cleaning continue

4. Setting out of:
– Ablution blocks
– Clocktower
– Road networks
– Car parks
– Storm and foul drainage

Other Pictures

1.150mm by 400mm concrete blocks, molded on site
Western hostel ring beam formwork fixing
Teachers' house

###
end update

Progress Report – October 25, 2024

Work continues, moving toward targets. […]

Read More

Progress Report – October 11, 2024

New targets set for month of October. […]

Read More

Progress Report – September 12, 2024

New completion date has been set; work continues. […]

Read More

Progress Report – August 23, 2024

Work continues on track. […]

Read More

Progress Report – August 16, 2024

Progress continues. […]

Read More

Progress Report – July 26, 2024

New targets set for August. […]

Read More

Progress Report – July 12, 2024

Work continues on track. […]

Read More

Progress Report – June 21, 2024

Overall progress on project is at 79%. […]

Read More

Progress Report – June 14, 2024

Progress continues on June targets. […]

Read More

Progress Report – May 31, 2024

Progress continues with new June targets established. […]

Read More