Updated April 15, 2025

Client: The Archdiocese of Blantyre
Consultant: Team Lift Inc. / Hagios Consulting Engineers
Contractor: Sitbec Ltd.

Proposed Contract Period: 80 weeks
Proposed Time Extension:  123 weeks
Proposed Commencement Date: January 2, 2023
Proposed Completion Date: December 31, 2024
Revised Completion Date: April 30, 2025
Time Elapsed: 120 weeks
Revised Elapsed Time Percentage: 97.56%
Overall Progress Percentage: 89.5%

Class Blocks (4 No)

West & Eastern Sections: Foul water drainage activities continue; Painting of external walls and trusses complete for class block NO.5; Storm water drainage system underway; Landscaping continues at both section (Eastern & Western)

Pavilion (4 No)

Eastern & Western Pavilions: Beam filling for pavilion NO. 7 & 11 complete; Internal wall plaster continues for pavilion NO. 7 & 11; Block work for pavilion 6 continues

Laboratory (2 No)

Western & Eastern Laboratory: Terrazzo installation laboratory NO. 10 complete worktop surfaces; Painting of trusses complete; Painting of walls continues at western laboratory; Foul water drainage activities on going western laboratory; Preparation of painting of doors underway

Administration

Preparations for tile fixing in progress; External wall paintings complete; Installation of electrical fittings continues; Landscaping in progress

Multipurpose

Painting of internal, external walls and trusses in progress; Preparation for external screed floor in progress; Fitting of external and internal doors complete; Pointing and window reveals complete

Western Hostels (No. 25)

Western Hostels (No.25 & 26): Landscaping in progress; Painting of trusses in progress at hostel NO. 25; Beam filling 90% done at hostel NO. 26, preparation for internal plaster underway

Eastern Hostels (No. 28)

Eastern Hostels (NO.28: Painting of trusses continues; Screed floor complete; Landscaping in progress

Library

Roofing in progress: Fixing of additional trusses & purlins continues

Teachers and Headmaster's House

Ceiling board installation in progress; Screed floor complete at headmasters house; Painting of external walls and trusses continues; Lime putty completed in all teachers houses; Preparation for screed floor under way house NO. 16 to 21

Cafeteria

Cafeteria: ready for screed floor

Staff Houses

Staff Houses: Ceiling board installation for house NO. 22 & 23 complete; Blundering for staff house NO. 24 95% complete; Screed floor for house 22 and 23 complete; Kitchen external plaster and pointing complete; Painting continues

Ablution Blocks
• Internal and external wall finishes continue

Rectory Extensions
• Land clearing complete
• Foundation excavation for the fence in progress

Convent
• Land clearing complete
• Setting out in progress

Note: The rest of the remaining activities to follow the executive summary


Other Works

External Works
– Septic tank

* Tanks 1 & 2: All remaining activities to resume soon

Sewer drainage system (western section 92%)
* Setting out, excavation, cleaning, sand level checking, pipe fixing & sand &
soil back filling, construction of manholes

– Earth works (75%)
* Road reshaping & gravel level refill to resume soon
* Crusher run final finish pending
* Ready for football pitch excavation and refill (delayed due to rains)

Electrical and Plumbing First and Second Phase Activities in progress (subcontractor)

Electrical and Plumbing Works:
First-phase activities in progress across all structures.

Other Pictures

Western classes aerial view
Eastern classes aerial view
Headmasters house screed floor complete
Foul water drainage
Conversion of pavillion no. 6 superstructure blockwork in progress
Foundation excavation for rectory perimeter fence
Site setting out for the convent building
Blockwork superstructure for eastern latrines up to ring beam level

###
end update

Meet Our Student Communications Team

As part of sharing the journey and stories of Our Lady of Namlenga High School, six students have been chosen to help write and communicate about life at the school. With their help, people from all over the world can get to know the students, teachers, and faculty that make up Our Lady of Namlenga. […]

Read More

Progress Report – December 5, 2025

Work progresses as our completion dates nears. […]

Read More

Progress Report – September 30, 2025

Work progresses as our completion dates nears. […]

Read More

Site Plan – October 08, 2025

Work progresses as our completion dates nears. […]

Read More

Progress Report – August 1, 2025

Work progresses as our completion dates nears. […]

Read More

Progress Report – June 20, 2025

Work moving along steadily as we work toward completion. […]

Read More

Progress Report – June 5, 2025

Work continues as we aim to finish by the end of Summer. […]

Read More

Progress Report – May 30, 2025

With the main buildings close to completion, efforts turn toward completing the rectory and playing fields. […]

Read More

Progress Report – May 23, 2025

Work continues as we progress toward our completion date. […]

Read More

Progress Report – May 9, 2025

Work will continue through the summer with a new completion date of August 31, 2025. […]