Updated February 28, 2024

Work continues. It is the hope of the contractor that the following works will be completed during the month of March 2024:

  • Completion of ring beam and block walls construction
  • Procurement, fabrication, and installation of steel roof trusses
  • Procurement of steel roof sheets, window and door frames, and setting out storm water and foul drainage structure.

Pictures of ongoing construction work can be seen below.

Administration Block

Superstructure ring beam preparations

Multipurpose Hall

Blockwork and basement work continues

Classrooms (2No)

Ring beam preparation in progress

Pavillions (2 No)

Column casting in progress

Laboratory (2 No)

Blockwork continues

Library

Superstructure blockwork

Staff Housing

Ring beam casting preparations

Hostels (2 No)

Superstructure blockwork setting in progress

Headmaster and Teachers' Housing

Ring beam preparations

Cafeteria

Ring beam preparations

Other Works

1. Block Moulding
181,553 blocks

2. Road Maintenance
Soil cutting and back filling

3. Site General Cleaning
Grass cutting and removal of broken block

Other Pictures

Library blockwork
Classrooms, lab, and pavilions
Headmaster's and teachers' housing
Middle section
Staff housing
Whole site view

###
end update

Progress Report – October 25, 2024

Work continues, moving toward targets. […]

Read More

Progress Report – October 11, 2024

New targets set for month of October. […]

Read More

Progress Report – September 12, 2024

New completion date has been set; work continues. […]

Read More

Progress Report – August 23, 2024

Work continues on track. […]

Read More

Progress Report – August 16, 2024

Progress continues. […]

Read More

Progress Report – July 26, 2024

New targets set for August. […]

Read More

Progress Report – July 12, 2024

Work continues on track. […]

Read More

Progress Report – June 21, 2024

Overall progress on project is at 79%. […]

Read More

Progress Report – June 14, 2024

Progress continues on June targets. […]

Read More

Progress Report – May 31, 2024

Progress continues with new June targets established. […]

Read More

HELP US

REACH OUR GOAL!

Working to complete Our Lady of Namulenga High School