Updated February 28, 2024
Work continues. It is the hope of the contractor that the following works will be completed during the month of March 2024:
- Completion of ring beam and block walls construction
- Procurement, fabrication, and installation of steel roof trusses
- Procurement of steel roof sheets, window and door frames, and setting out storm water and foul drainage structure.
Pictures of ongoing construction work can be seen below.
Administration Block

Multipurpose Hall

Classrooms (2No)

Pavillions (2 No)

Laboratory (2 No)

Library

Staff Housing

Hostels (2 No)

Headmaster and Teachers' Housing

Cafeteria

Other Works
1. Block Moulding
181,553 blocks
2. Road Maintenance
Soil cutting and back filling
3. Site General Cleaning
Grass cutting and removal of broken block
Other Pictures






###
end update