Updated February 28, 2024

Work continues. It is the hope of the contractor that the following works will be completed during the month of March 2024:

  • Completion of ring beam and block walls construction
  • Procurement, fabrication, and installation of steel roof trusses
  • Procurement of steel roof sheets, window and door frames, and setting out storm water and foul drainage structure.

Pictures of ongoing construction work can be seen below.

Administration Block

Superstructure ring beam preparations

Multipurpose Hall

Blockwork and basement work continues

Classrooms (2No)

Ring beam preparation in progress

Pavillions (2 No)

Column casting in progress

Laboratory (2 No)

Blockwork continues

Library

Superstructure blockwork

Staff Housing

Ring beam casting preparations

Hostels (2 No)

Superstructure blockwork setting in progress

Headmaster and Teachers' Housing

Ring beam preparations

Cafeteria

Ring beam preparations

Other Works

1. Block Moulding
181,553 blocks

2. Road Maintenance
Soil cutting and back filling

3. Site General Cleaning
Grass cutting and removal of broken block

Other Pictures

Library blockwork
Classrooms, lab, and pavilions
Headmaster's and teachers' housing
Middle section
Staff housing
Whole site view

###
end update

Progress Report – December 5, 2025

Work progresses as our completion dates nears. […]

Read More

Progress Report – September 30, 2025

Work progresses as our completion dates nears. […]

Read More

Site Plan – October 08, 2025

Work progresses as our completion dates nears. […]

Read More

Progress Report – August 1, 2025

Work progresses as our completion dates nears. […]

Read More

Progress Report – June 20, 2025

Work moving along steadily as we work toward completion. […]

Read More

Progress Report – June 5, 2025

Work continues as we aim to finish by the end of Summer. […]

Read More

Progress Report – May 30, 2025

With the main buildings close to completion, efforts turn toward completing the rectory and playing fields. […]

Read More

Progress Report – May 23, 2025

Work continues as we progress toward our completion date. […]

Read More

Progress Report – May 9, 2025

Work will continue through the summer with a new completion date of August 31, 2025. […]

Read More

Progress Report – April 11, 2025

Progress continues as we work toward a completion date of April 30, 2025. […]

Read More

HELP US

REACH OUR GOAL!

Working to complete Our Lady of Namulenga High School