Updated June 17, 2024

Client: The Archdiocese of Blantyre
Consultant: Team Lift Inc. / Hagios Consulting Engineers
Contractor: Sitbec Ltd.

Proposed Contract Period: 80 weeks
Proposed Time Extension:  9 weeks
Proposed Commencement Date: January 2, 2023
Proposed Completion Date: July 2, 2024
Revised Completion Date: August 31, 2024
Time Elapsed: 75 weeks
Elapsed Time Percentage: 93.7%
Revised Elapsed Time Percentage: 84%
Overall Progress Percentage: 77.5%

JUNE TARGETS:

– Fabrication and installation of steel roof trusses continues.
– Window and door frame fabrication and fixing continues.
– Main site road networks continues.
– Superstructure wall finishes continues.

Pictures of work in progress can be see below.

Administration Block

Superstructure wall finishes. Inside wall first plastering complete; Outside wall finishes continues; Door and window frames fixing continues.

Multipurpose Hall

Superstructure wall finishes and Trusses; Inside wall finishes continues.

Classrooms (2No)

WALL FINISHES CONTINUES; Outside wall finishes continues

Pavillions (2 No)

TRUSSES PREPARATIONS STILL IN PROGRESS; Installation of U-bolt

Laboratory (1 No)

TRUSSES ALIGNMENT AND WALL FINISHES; Inside room sink benches slabs in progress; Outside room wall finishes continues

Library

ROOF BEAM ACTIVITIES AND WALL FINISHES Finalizing roof beam concrete casting; Inside wall first plastering complete

Staff Housing

TRUSSES AND WALL FINISHES Inside wall first plastering complete; Trusses in progress

Hostels (2 No)

TRUSSES AND WALL FINISHES Inside room first wall finishes in progress

Headmaster and Teachers' Housing

TRUSSES CONTINUES Inside room first wall plastering complete

Cafeteria

TRUSSES AND WALL FINISHES STILL IN PROGRESS Inside rooms first plastering complete

Other Works

Ablution Blocks & Clocktower
– foundation slab concrete casting in progress

foundation slab concrete casting in progress

Fabrication & fixing of trusses, door & window frames continues

trusses
frame

External Works:
– Septic tank trench excavation
– Road network

* soil cutting
* road formation soil clarification, mixing and compaction

road network
Septic tank trench excavation

Electrical and Plumbing First Phase Activities in Progress

Site general cleaning continues

Other Pictures

main site road works
main site road carpark works
classroom outside wall finishes
inside Laboratory wall sink tables blockwork
Hostel washroom plaster finishes & plumbing works
ESCOM power line reroute materials
ESCOM power line reroute materials
ESCOM power line reroute materials

###
end update

Progress Report – October 25, 2024

Work continues, moving toward targets. […]

Read More

Progress Report – October 11, 2024

New targets set for month of October. […]

Read More

Progress Report – September 12, 2024

New completion date has been set; work continues. […]

Read More

Progress Report – August 23, 2024

Work continues on track. […]

Read More

Progress Report – August 16, 2024

Progress continues. […]

Read More

Progress Report – July 26, 2024

New targets set for August. […]

Read More

Progress Report – July 12, 2024

Work continues on track. […]

Read More

Progress Report – June 21, 2024

Overall progress on project is at 79%. […]

Read More

Progress Report – May 31, 2024

Progress continues with new June targets established. […]

Read More

Progress Report – May 17, 2024

Overall completion percentage at 74.5%. […]

Read More

HELP US

REACH OUR GOAL!

Working to complete Our Lady of Namulenga High School