Updated June 17, 2024

Client: The Archdiocese of Blantyre
Consultant: Team Lift Inc. / Hagios Consulting Engineers
Contractor: Sitbec Ltd.

Proposed Contract Period: 80 weeks
Proposed Time Extension:  9 weeks
Proposed Commencement Date: January 2, 2023
Proposed Completion Date: July 2, 2024
Revised Completion Date: August 31, 2024
Time Elapsed: 75 weeks
Elapsed Time Percentage: 93.7%
Revised Elapsed Time Percentage: 84%
Overall Progress Percentage: 77.5%

JUNE TARGETS:

– Fabrication and installation of steel roof trusses continues.
– Window and door frame fabrication and fixing continues.
– Main site road networks continues.
– Superstructure wall finishes continues.

Pictures of work in progress can be see below.

Administration Block

Superstructure wall finishes. Inside wall first plastering complete; Outside wall finishes continues; Door and window frames fixing continues.

Multipurpose Hall

Superstructure wall finishes and Trusses; Inside wall finishes continues.

Classrooms (2No)

WALL FINISHES CONTINUES; Outside wall finishes continues

Pavillions (2 No)

TRUSSES PREPARATIONS STILL IN PROGRESS; Installation of U-bolt

Laboratory (1 No)

TRUSSES ALIGNMENT AND WALL FINISHES; Inside room sink benches slabs in progress; Outside room wall finishes continues

Library

ROOF BEAM ACTIVITIES AND WALL FINISHES Finalizing roof beam concrete casting; Inside wall first plastering complete

Staff Housing

TRUSSES AND WALL FINISHES Inside wall first plastering complete; Trusses in progress

Hostels (2 No)

TRUSSES AND WALL FINISHES Inside room first wall finishes in progress

Headmaster and Teachers' Housing

TRUSSES CONTINUES Inside room first wall plastering complete

Cafeteria

TRUSSES AND WALL FINISHES STILL IN PROGRESS Inside rooms first plastering complete

Other Works

Ablution Blocks & Clocktower
– foundation slab concrete casting in progress

foundation slab concrete casting in progress

Fabrication & fixing of trusses, door & window frames continues

trusses
frame

External Works:
– Septic tank trench excavation
– Road network

* soil cutting
* road formation soil clarification, mixing and compaction

road network
Septic tank trench excavation

Electrical and Plumbing First Phase Activities in Progress

Site general cleaning continues

Other Pictures

main site road works
main site road carpark works
classroom outside wall finishes
inside Laboratory wall sink tables blockwork
Hostel washroom plaster finishes & plumbing works
ESCOM power line reroute materials
ESCOM power line reroute materials
ESCOM power line reroute materials

###
end update

Progress Report – December 5, 2025

Work progresses as our completion dates nears. […]

Read More

Progress Report – September 30, 2025

Work progresses as our completion dates nears. […]

Read More

Site Plan – October 08, 2025

Work progresses as our completion dates nears. […]

Read More

Progress Report – August 1, 2025

Work progresses as our completion dates nears. […]

Read More

Progress Report – June 20, 2025

Work moving along steadily as we work toward completion. […]

Read More

Progress Report – June 5, 2025

Work continues as we aim to finish by the end of Summer. […]

Read More

Progress Report – May 30, 2025

With the main buildings close to completion, efforts turn toward completing the rectory and playing fields. […]

Read More

Progress Report – May 23, 2025

Work continues as we progress toward our completion date. […]

Read More

Progress Report – May 9, 2025

Work will continue through the summer with a new completion date of August 31, 2025. […]

Read More

Progress Report – April 11, 2025

Progress continues as we work toward a completion date of April 30, 2025. […]

Read More

HELP US

REACH OUR GOAL!

Working to complete Our Lady of Namulenga High School