Updated June 17, 2024
Client: The Archdiocese of Blantyre
Consultant: Team Lift Inc. / Hagios Consulting Engineers
Contractor: Sitbec Ltd.
Proposed Contract Period: 80 weeks
Proposed Time Extension:Â 9 weeks
Proposed Commencement Date: January 2, 2023
Proposed Completion Date: July 2, 2024
Revised Completion Date: August 31, 2024
Time Elapsed: 75 weeks
Elapsed Time Percentage: 93.7%
Revised Elapsed Time Percentage: 84%
Overall Progress Percentage: 77.5%
JUNE TARGETS:
– Fabrication and installation of steel roof trusses continues.
– Window and door frame fabrication and fixing continues.
– Main site road networks continues.
– Superstructure wall finishes continues.
Pictures of work in progress can be see below.
Administration Block

Multipurpose Hall

Classrooms (2No)

Pavillions (2 No)

Laboratory (1 No)

Library

Staff Housing

Hostels (2 No)

Headmaster and Teachers' Housing

Cafeteria

Other Works
Ablution Blocks & Clocktower
– foundation slab concrete casting in progress

Fabrication & fixing of trusses, door & window frames continues


External Works:
– Septic tank trench excavation
– Road network
* soil cutting
* road formation soil clarification, mixing and compaction


Electrical and Plumbing First Phase Activities in Progress
Site general cleaning continues
Other Pictures








###
end update