Updated April 29, 2024
Client: The Archdiocese of Blantyre
Consultant: Team Lift Inc. / Hagios Consulting Engineers
Contractor: Sitbec Ltd.
Proposed Contract Period: 80 weeks
Proposed Time Extension:Â 9 weeks
Proposed Commencement Date: January 2, 2023
Proposed Completion Date: July 2, 2024
Revised Completion Date: August 31, 2024
Time Elapsed: 67 weeks
Elapsed Time Percentage: 83.75%
Revised Elapsed Time Percentage: 75.28%
Overall Progress Percentage: 72%
APRIL TARGETS:
Procurement, fabrication, and installation of steel roof trusses:
– Work has started with fabrication and most of the steel has been procured from South Africa.
Procurement of steel roof sheets, window and door frames:
– Window and door frames are being fabricated locally.
Fixing of door and window frames:
– Not started yet.
Plastering:
– We have started on some structures.
Setting out storm water and foul drainage structures:
– We are doing road alignment sampling to determine the road and drainage designs.
Setting out of ablution blocks and clocktower:
– In progress.
Pictures of work in progress can be see below.
Administration Block

Multipurpose Hall

Classrooms (2No)

Pavillions (2 No)

Laboratory (2 No)

Library

Staff Housing

Hostels (2 No)

Headmaster and Teachers' Housing

Cafeteria

Other Works
Block Moulding
269,300 blocks
Setting out of:
– Ablution blocks: done
– Clocktower: done
– Road networks: done
– Carparks: done
– Storm and foul drainages: continues
– Soil sampling, field and lab tests: in progress
Electrical and plumbing first phase activities in progress
Site general cleaning continues
Fabrication and assembling of trusses continues