Updated April 8, 2024

April targets:

  • Procurement, fabrication, and installation of steel roof trusses
  • Procurement of steel roof sheets, window and door frames
  • Fixing door and window frames
  • Plastering
  • Setting out storm water and foul drainage structures
  • Setting out of ablution blocks and clocktower

Pictures of ongoing construction work can be seen below.

Administration Block

Ready for roofing

Multipurpose Hall

Finalizing rebar fixing (slab to be cast tomorrow)

Classrooms (2No)

Finalizing after beam blockwork

Pavillions (2 No)

Ring beam formwork and rebar preparations

Laboratory (1 No)

Finalizing after ring beam blockwork

Library

Fixing of ring beam formwork

Staff Housing (3 No)

After beam blockwork continues

Hostels (2 No)

Ring beam formwork and rebar fixing continues

Headmaster and Teachers' Housing

Ring beam casting done; blockwork continues

Cafeteria

Blockwork continues

Other Works

1. Block Moulding
245,000 blocks

2. Electrical and plumbing first phase activities in progress

3. Site general cleaning continue

4. Setting out of:
– Ablution blocks
– Clocktower
– Road networks
– Car parks
– Storm and foul drainage

Other Pictures

1.150mm by 400mm concrete blocks, molded on site
Western hostel ring beam formwork fixing
Teachers' house

###
end update

Meet Our Student Communications Team

As part of sharing the journey and stories of Our Lady of Namlenga High School, six students have been chosen to help write and communicate about life at the school. With their help, people from all over the world can get to know the students, teachers, and faculty that make up Our Lady of Namlenga. […]

Read More

Progress Report – December 5, 2025

Work progresses as our completion dates nears. […]

Read More

Progress Report – September 30, 2025

Work progresses as our completion dates nears. […]

Read More

Site Plan – October 08, 2025

Work progresses as our completion dates nears. […]

Read More

Progress Report – August 1, 2025

Work progresses as our completion dates nears. […]

Read More

Progress Report – June 20, 2025

Work moving along steadily as we work toward completion. […]

Read More

Progress Report – June 5, 2025

Work continues as we aim to finish by the end of Summer. […]

Read More

Progress Report – May 30, 2025

With the main buildings close to completion, efforts turn toward completing the rectory and playing fields. […]

Read More

Progress Report – May 23, 2025

Work continues as we progress toward our completion date. […]

Read More

Progress Report – May 9, 2025

Work will continue through the summer with a new completion date of August 31, 2025. […]

Read More

HELP US

REACH OUR GOAL!

Working to complete Our Lady of Namulenga High School