Updated July 30, 2023

Work continues to progress. Unfortunately, there is currently an economic crisis prevailing in Malawi – fuel shortages. This has resulted in costs/prices of goods and services to skyrocket. This situation has affected the progress of on-going work on site. The contractor is unable to utilize the back-hoe machines to aid in the excavation process, thus resorting to manual digging. That notwithstanding, considerable progress is being made as the morale of the workers on site is very high.

Pictures of ongoing construction work can be seen below.

Administration Block

Setting out: 100% | Excavation: 100% | Sand blinding and leveling: 100% | Underground beam rebars fabrication: 50%

Multipurpose Hall

Setting out: 100% | Excavations: 100% | Leveling: 50%

Western Classrooms

Setting Out: 100% | Excavations: 75%
Leveling: 50%

Western Laboratory (1No)

Setting: 100% | Excavations: 65%

Western Pavilions (2No)

Setting: 100% | Excavation: 70%
Leveling: 50%

Eastern Classrooms (2 No)

Setting Out: 100% | Excavations: 70%
Leveling: 45%

Eastern Laboratory (1 No)

Setting Out: 100% | Excavation & cleaning: 45%

2 Eastern Pavilions

Setting Out: 95%
Excavations: 50%

Library

Setting Out: 100%
Excavation: 60%

Western Hostels (3 No)

Setting Out: 45%

Staff Housing

Setting Out: 80%

Headmaster and Teachers’ Housing

Setting Out: 100%
Excavation & Cleaning: 30%

Structures being set out now:

  • Eastern hostels (3No)
  • The clock tower (location not yet identified as of last site meeting.)

###
end update

Progress Report – December 5, 2025

Work progresses as our completion dates nears. […]

Read More

Progress Report – September 30, 2025

Work progresses as our completion dates nears. […]

Read More

Site Plan – October 08, 2025

Work progresses as our completion dates nears. […]

Read More

Progress Report – August 1, 2025

Work progresses as our completion dates nears. […]

Read More

Progress Report – June 20, 2025

Work moving along steadily as we work toward completion. […]

Read More

Progress Report – June 5, 2025

Work continues as we aim to finish by the end of Summer. […]

Read More

Progress Report – May 30, 2025

With the main buildings close to completion, efforts turn toward completing the rectory and playing fields. […]

Read More

Progress Report – May 23, 2025

Work continues as we progress toward our completion date. […]

Read More

Progress Report – May 9, 2025

Work will continue through the summer with a new completion date of August 31, 2025. […]

Read More

Progress Report – April 11, 2025

Progress continues as we work toward a completion date of April 30, 2025. […]

Read More

HELP US

REACH OUR GOAL!

Working to complete Our Lady of Namulenga High School