Updated July 30, 2023

Work continues to progress. Unfortunately, there is currently an economic crisis prevailing in Malawi – fuel shortages. This has resulted in costs/prices of goods and services to skyrocket. This situation has affected the progress of on-going work on site. The contractor is unable to utilize the back-hoe machines to aid in the excavation process, thus resorting to manual digging. That notwithstanding, considerable progress is being made as the morale of the workers on site is very high.

Pictures of ongoing construction work can be seen below.

Administration Block

Setting out: 100% | Excavation: 100% | Sand blinding and leveling: 100% | Underground beam rebars fabrication: 50%

Multipurpose Hall

Setting out: 100% | Excavations: 100% | Leveling: 50%

Western Classrooms

Setting Out: 100% | Excavations: 75%
Leveling: 50%

Western Laboratory (1No)

Setting: 100% | Excavations: 65%

Western Pavilions (2No)

Setting: 100% | Excavation: 70%
Leveling: 50%

Eastern Classrooms (2 No)

Setting Out: 100% | Excavations: 70%
Leveling: 45%

Eastern Laboratory (1 No)

Setting Out: 100% | Excavation & cleaning: 45%

2 Eastern Pavilions

Setting Out: 95%
Excavations: 50%

Library

Setting Out: 100%
Excavation: 60%

Western Hostels (3 No)

Setting Out: 45%

Staff Housing

Setting Out: 80%

Headmaster and Teachers’ Housing

Setting Out: 100%
Excavation & Cleaning: 30%

Structures being set out now:

  • Eastern hostels (3No)
  • The clock tower (location not yet identified as of last site meeting.)

###
end update

Progress Report – October 25, 2024

Work continues, moving toward targets. […]

Read More

Progress Report – October 11, 2024

New targets set for month of October. […]

Read More

Progress Report – September 12, 2024

New completion date has been set; work continues. […]

Read More

Progress Report – August 23, 2024

Work continues on track. […]

Read More

Progress Report – August 16, 2024

Progress continues. […]

Read More

Progress Report – July 26, 2024

New targets set for August. […]

Read More

Progress Report – July 12, 2024

Work continues on track. […]

Read More

Progress Report – June 21, 2024

Overall progress on project is at 79%. […]

Read More

Progress Report – June 14, 2024

Progress continues on June targets. […]

Read More

Progress Report – May 31, 2024

Progress continues with new June targets established. […]