Updated April 15, 2025

Client: The Archdiocese of Blantyre
Consultant: Team Lift Inc. / Hagios Consulting Engineers
Contractor: Sitbec Ltd.

Proposed Contract Period: 80 weeks
Proposed Time Extension:  123 weeks
Proposed Commencement Date: January 2, 2023
Proposed Completion Date: December 31, 2024
Revised Completion Date: April 30, 2025
Time Elapsed: 120 weeks
Revised Elapsed Time Percentage: 97.56%
Overall Progress Percentage: 89.5%

Class Blocks (4 No)

West & Eastern Sections: Foul water drainage activities continue; Painting of external walls and trusses complete for class block NO.5; Storm water drainage system underway; Landscaping continues at both section (Eastern & Western)

Pavilion (4 No)

Eastern & Western Pavilions: Beam filling for pavilion NO. 7 & 11 complete; Internal wall plaster continues for pavilion NO. 7 & 11; Block work for pavilion 6 continues

Laboratory (2 No)

Western & Eastern Laboratory: Terrazzo installation laboratory NO. 10 complete worktop surfaces; Painting of trusses complete; Painting of walls continues at western laboratory; Foul water drainage activities on going western laboratory; Preparation of painting of doors underway

Administration

Preparations for tile fixing in progress; External wall paintings complete; Installation of electrical fittings continues; Landscaping in progress

Multipurpose

Painting of internal, external walls and trusses in progress; Preparation for external screed floor in progress; Fitting of external and internal doors complete; Pointing and window reveals complete

Western Hostels (No. 25)

Western Hostels (No.25 & 26): Landscaping in progress; Painting of trusses in progress at hostel NO. 25; Beam filling 90% done at hostel NO. 26, preparation for internal plaster underway

Eastern Hostels (No. 28)

Eastern Hostels (NO.28: Painting of trusses continues; Screed floor complete; Landscaping in progress

Library

Roofing in progress: Fixing of additional trusses & purlins continues

Teachers and Headmaster's House

Ceiling board installation in progress; Screed floor complete at headmasters house; Painting of external walls and trusses continues; Lime putty completed in all teachers houses; Preparation for screed floor under way house NO. 16 to 21

Cafeteria

Cafeteria: ready for screed floor

Staff Houses

Staff Houses: Ceiling board installation for house NO. 22 & 23 complete; Blundering for staff house NO. 24 95% complete; Screed floor for house 22 and 23 complete; Kitchen external plaster and pointing complete; Painting continues

Ablution Blocks
• Internal and external wall finishes continue

Rectory Extensions
• Land clearing complete
• Foundation excavation for the fence in progress

Convent
• Land clearing complete
• Setting out in progress

Note: The rest of the remaining activities to follow the executive summary


Other Works

External Works
– Septic tank

* Tanks 1 & 2: All remaining activities to resume soon

Sewer drainage system (western section 92%)
* Setting out, excavation, cleaning, sand level checking, pipe fixing & sand &
soil back filling, construction of manholes

– Earth works (75%)
* Road reshaping & gravel level refill to resume soon
* Crusher run final finish pending
* Ready for football pitch excavation and refill (delayed due to rains)

Electrical and Plumbing First and Second Phase Activities in progress (subcontractor)

Electrical and Plumbing Works:
First-phase activities in progress across all structures.

Other Pictures

Western classes aerial view
Eastern classes aerial view
Headmasters house screed floor complete
Foul water drainage
Conversion of pavillion no. 6 superstructure blockwork in progress
Foundation excavation for rectory perimeter fence
Site setting out for the convent building
Blockwork superstructure for eastern latrines up to ring beam level

###
end update

Progress Report – December 5, 2025

Work progresses as our completion dates nears. […]

Read More

Progress Report – September 30, 2025

Work progresses as our completion dates nears. […]

Read More

Site Plan – October 08, 2025

Work progresses as our completion dates nears. […]

Read More

Progress Report – August 1, 2025

Work progresses as our completion dates nears. […]

Read More

Progress Report – June 20, 2025

Work moving along steadily as we work toward completion. […]

Read More

Progress Report – June 5, 2025

Work continues as we aim to finish by the end of Summer. […]

Read More

Progress Report – May 30, 2025

With the main buildings close to completion, efforts turn toward completing the rectory and playing fields. […]

Read More

Progress Report – May 23, 2025

Work continues as we progress toward our completion date. […]

Read More

Progress Report – May 9, 2025

Work will continue through the summer with a new completion date of August 31, 2025. […]

Read More

Progress Report – March 28, 2025

We’re in the home stretch! Aiming for a completion date of April 30, 2025. […]

Read More