Updated April 15, 2025
Client: The Archdiocese of Blantyre
Consultant: Team Lift Inc. / Hagios Consulting Engineers
Contractor: Sitbec Ltd.
Proposed Contract Period: 80 weeks
Proposed Time Extension: 123 weeks
Proposed Commencement Date: January 2, 2023
Proposed Completion Date: December 31, 2024
Revised Completion Date: April 30, 2025
Time Elapsed: 120 weeks
Revised Elapsed Time Percentage: 97.56%
Overall Progress Percentage: 89.5%
Class Blocks (4 No)

Pavilion (4 No)

Laboratory (2 No)

Administration

Multipurpose

Western Hostels (No. 25)

Eastern Hostels (No. 28)

Library

Teachers and Headmaster's House

Cafeteria

Staff Houses

Ablution Blocks
• Internal and external wall finishes continue
Rectory Extensions
• Land clearing complete
• Foundation excavation for the fence in progress
Convent
• Land clearing complete
• Setting out in progress
Note: The rest of the remaining activities to follow the executive summary
Other Works
External Works
– Septic tank
* Tanks 1 & 2: All remaining activities to resume soon
Sewer drainage system (western section 92%)
* Setting out, excavation, cleaning, sand level checking, pipe fixing & sand &
soil back filling, construction of manholes
– Earth works (75%)
* Road reshaping & gravel level refill to resume soon
* Crusher run final finish pending
* Ready for football pitch excavation and refill (delayed due to rains)
Electrical and Plumbing First and Second Phase Activities in progress (subcontractor)
Electrical and Plumbing Works:
First-phase activities in progress across all structures.
Other Pictures








###
end update