Updated May 27, 2025

Client: The Archdiocese of Blantyre
Consultant: Team Lift Inc. / Hagios Consulting Engineers
Contractor: Sitbec Ltd.

Proposed Contract Period: 80 weeks
Proposed Time Extension:  141 weeks
Proposed Commencement Date: January 2, 2023
Proposed Completion Date: December 31, 2024
Revised Completion Date: August 31, 2025
Time Elapsed: 124 weeks
Revised Elapsed Time Percentage: 89.36%
Overall Progress Percentage: 89.5%

Class Blocks (4 No)

Eastern & Western teaching area section

• Storm water drainage in progress at western section
• Landscaping continues at western section
• Finalizing of painting at classroom NO.3 in progress

Pavilion (4 No)

Superstructure blockwork for pavilion NO.12 in progress

• Lime putty complete at pavilion NO.7 & 11
• Screed floor complete at pavilion NO.7
• Preparation for screed floor at pavilion NO.11 in progress
• Internal plaster to resume soon for pavilion NO.6
• Blockwork for pavilion NO.12 in progress
• Fascia board installation for pavilion NO.6 in progress
• Preparation for Blackboard installation in progress

Laboratory (2 No)

Terrazzo installation at western laboratory

• Terrazzo installation complete both eastern and western section
• Painting of external and internal walls continues

Administration

Internal wall painting complete

• Internal and external wall paintings complete
• Installation of electrical fittings continues
• Door fitting to resume soon
• Storm water drainage complete

Multipurpose

Aerial view for multipurpose hall

• Painting of internal, external walls and trusses continues
• External screed floor complete
• Storm water drainage complete

Western Hostels (No. 25, 26, & 27)

Western hostel no 25 plaster primer painting

• Painting of trusses completed for hostel NO.25
• Painting of internal wall in progress at hostel NO.25
• Preparation for pointing & foundation plaster in progress for hostel NO.25
• Lime putty in progress for hostel NO.27

Eastern Hostels (No. 28 & 29)

Aerial view for western hostels

• Painting of trusses in progress for hostel NO.28
• Preparation for external plaster & pointing in progress at hostel No.
• Internal wall plastering complete at hostel NO.29

Library

Roofing continues at library

• Painting of trusses continues
• Welding of purlins in progress

Teachers and Headmaster's House

Foundation plaster in progress

• Ceiling board installation complete for teachers house NO. 15 to 20
• Blundering continues for house number 21
• Foundation plaster in progress for house NO. 15 to 21 in progress
• Painting of internal walls for head masters house in progress
• Preparation for painting for house NO 16 to 21 in progress
• Screed floor to commence soon for house NO. 16 to 21

Cafeteria

Aerial view for cafeteria

• Screed floor completed
• Foundation plaster in progress
• Storm water drainage system to commence
• Foul drainage system completed

Staff Houses

Aerial view for staff houses

• Ceiling board painting in progress
• Kitchen sink basin fitting to commerce soon
• Foundation plaster completed
• Preparation for storm water drainage in progress

Ablution Blocks/ Pit Latrines
• Internal and external wall finishes continue
• Casting of concrete column pillars at eastern latrines completed

Rectory Extensions

Preparation for slab casting in progress at extension site

• Block work for perimeter wall complete
• Substructure at extension site completed and is ready for slab casting

Convent
• Footing casting in progress
• Block work in progress

Note: The rest of the remaining activities to follow the executive summary

Rectory Extensions

Aerial view for convent substructure

Other Works

External Works
– Septic tank

* Tanks 1 & 2: All remaining activities to resume soon

Sewer drainage system (western section 92%)
* Setting out, excavation, cleaning, sand level checking, pipe fixing & sand &
soil back filling, construction of manholes

– Earth works (75%)
* Road reshaping & gravel level refill to resume soon
* Crusher run final finish pending
* Ready for football pitch excavation and refill (delayed due to rains)

Electrical and Plumbing First and Second Phase Activities in progress (subcontractor)

Other Pictures

Site aerial view

###
end update

Meet Our Student Communications Team

As part of sharing the journey and stories of Our Lady of Namlenga High School, six students have been chosen to help write and communicate about life at the school. With their help, people from all over the world can get to know the students, teachers, and faculty that make up Our Lady of Namlenga. […]

Read More

Progress Report – December 5, 2025

Work progresses as our completion dates nears. […]

Read More

Progress Report – September 30, 2025

Work progresses as our completion dates nears. […]

Read More

Site Plan – October 08, 2025

Work progresses as our completion dates nears. […]

Read More

Progress Report – August 1, 2025

Work progresses as our completion dates nears. […]

Read More

Progress Report – June 20, 2025

Work moving along steadily as we work toward completion. […]

Read More

Progress Report – June 5, 2025

Work continues as we aim to finish by the end of Summer. […]

Read More

Progress Report – May 30, 2025

With the main buildings close to completion, efforts turn toward completing the rectory and playing fields. […]

Read More

Progress Report – May 9, 2025

Work will continue through the summer with a new completion date of August 31, 2025. […]

Read More

Progress Report – April 11, 2025

Progress continues as we work toward a completion date of April 30, 2025. […]

Read More