Updated August 13, 2025

Client: The Archdiocese of Blantyre
Consultant: Team Lift Inc. / Hagios Consulting Engineers
Contractor: Sitbec Ltd.

Proposed Contract Period: 80 weeks
Proposed Time Extension:  141 weeks
Proposed Commencement Date: January 2, 2023
Proposed Completion Date: December 31, 2024
Revised Completion Date: August 31, 2025
Time Elapsed: 135 weeks
Revised Elapsed Time Percentage: 95%
Overall Progress Percentage: 93%

Class Blocks (4 No)

Western teaching area section

Western & Eastern Sections

  • Cleaning of window glasses, screed floor and wall paints completed
    painting of internal doors complete
  • Painting of blackboards complete
  • Storm water 95% complete at western section

Pavilion (4 No)

Western pavilion section

Eastern & Western Pavilions

  • Window reveals for pavilion NO.12 complete
  • Column polishing in progress
  • Painting of internal and external wall in progress.
  • Storm water drain 95% complete

Laboratory (2 No)

Finalizing storm water drain at Western Lab

Western and Eastern Laboratory

  • Terrazzo polishing complete
  • Ramps and step construction complete
  • Plumbing fitting 85% complete
  • Painting of internal wall (second coat)in progress
  • Storm water drain 97% complete

Administration & Clocktower

External view of Administration
  • Construction of masonry wall in progress
  • Installation of plumbing fittings complete
  • Painting of internal doors complete

Clocktower

Clock tower painting in progress
  • External wall painting completed
  • Pointing completed
  • Storm water drain to resume soon

Multipurpose

Aerial view of Multipurpose Hall
  • Painting of trusses to resume soon
  • Painting of external doors complete
  • Painting of stairway basement side walls complete

Hostels

Western hostel painting in progress

Western Hostels (NO.25)

  • Painting of internal walls (second coat) to resume soon
  • Cleaning in progress
  • Storm water drainage to resume soon
  • Door fitting completed
  • Plumbing fitting completed

Eastern Hostels (No. 28)

Aerial view of Western hostel

Eastern Hostels (NO.28)

  • External and internal wall painting continues
  • Storm water drainage to resume soon
  • Door fitting in progress
  • Plumbing fittings to resume soon

Library

Library aerial view
  • Painting of trusses complete
  • Painting in progress
  • Construction of ramps and steps 90% complete
  • Screed floor in progress

Teachers and Headmaster's House

Aerial view of teachers' houses
  • Cornice installation complete for house number NO.15 to 20
  • Preparation for Internal doors painting in progress
  • Painting of internal walls (second coat) in progress
  • Storm water drainage to resume soon
  • Plumbing fitting complete for house NO.15 to 21
  • Preparation for masonry wall in progress
  • Electrical fittings 90% complete

Cafeteria

Aerial view of cafeteria
  • Painting of internal walls to resume soon
  • Storm water drainage system to commence soon
  • Door fitting complete
  • Painting of trusses complete

Staff Houses

Aerial view of Staff Houses
  • Door fitting complete
  • Storm water drainage to resume soon
  • Painting of external and internal wall in progress
  • Installation of external plumbing fittings 90% complete
  • Installation of electrical fittings in progress

Western and Eastern Ablution blocks

Eastern Ablution aerial view
  • Screed floor complete for all ablution blocks
  • Door fittings complete for all ablution blocks
  • Screen wall 90% complete
  • Storm water drain to resume soon

Other Works

External Works
– Septic tank: Tank 1, 2, and 3

* Construction of cafeteria septic tank in progress
* Construction of soak way pit to commence soon

Sewer drainage system by sub-contractor 94%
* The sewer line system installation, including all piping completed
* Manholes construction in progress

– Earth works (75%)
* Road reshaping & gravel level refill to resume soon (delayed due to heavy rains)
* Crusher run final finish pending

Electrical and Plumbing First and Second Phase Activities in progress (subcontractor)

Other Pictures

Aerial site view

###
end update

Meet Our Student Communications Team

As part of sharing the journey and stories of Our Lady of Namlenga High School, six students have been chosen to help write and communicate about life at the school. With their help, people from all over the world can get to know the students, teachers, and faculty that make up Our Lady of Namlenga. […]

Read More

Progress Report – December 5, 2025

Work progresses as our completion dates nears. […]

Read More

Progress Report – September 30, 2025

Work progresses as our completion dates nears. […]

Read More

Site Plan – October 08, 2025

Work progresses as our completion dates nears. […]

Read More

Progress Report – June 20, 2025

Work moving along steadily as we work toward completion. […]

Read More

Progress Report – June 5, 2025

Work continues as we aim to finish by the end of Summer. […]

Read More

Progress Report – May 30, 2025

With the main buildings close to completion, efforts turn toward completing the rectory and playing fields. […]

Read More

Progress Report – May 23, 2025

Work continues as we progress toward our completion date. […]

Read More

Progress Report – May 9, 2025

Work will continue through the summer with a new completion date of August 31, 2025. […]

Read More

Progress Report – April 11, 2025

Progress continues as we work toward a completion date of April 30, 2025. […]

Read More