Updated June 3, 2025

Client: The Archdiocese of Blantyre
Consultant: Team Lift Inc. / Hagios Consulting Engineers
Contractor: Sitbec Ltd.

Proposed Contract Period: 80 weeks
Proposed Time Extension:  141 weeks
Proposed Commencement Date: January 2, 2023
Proposed Completion Date: December 31, 2024
Revised Completion Date: August 31, 2025
Time Elapsed: 127 weeks
Revised Elapsed Time Percentage: 90.1%
Overall Progress Percentage: 89.5%

Class Blocks (4 No)

Eastern & Western teaching area section

• Storm water drainage in progress at western section
• Landscaping continues at western section
• Finalizing of painting at classroom NO.3 in progress

Pavilion (4 No)

Superstructure block-work for pavilion NO.12 in progress

• Lime putty complete at pavilion NO.7 & 11
• Screed floor complete at pavilion NO.7 & 11
• Blackboard installation complete for pavilion NO.7
• Preparation blackboard installation in progress for pavilion NO.1
• Internal plaster & pointing complete for pavilion NO.6
• Block-work for pavilion NO.12 in progress
• Fascia board installation for pavilion NO.6 in progress

Laboratory (2 No)

Terrazzo installation at western laboratory

• Terrazzo installation complete both eastern and western section
• Painting of external and internal walls continues

Administration

Internal wall painting complete

• Internal and external wall paintings complete
• Installation of electrical fittings continues
• Door fitting to resume soon
• Storm water drainage complete

Multipurpose

Aerial view for multipurpose hall

• Painting of internal, external walls and trusses continues
• External screed floor complete
• Storm water drainage complete
• Veranda skirting in progress

Western Hostels (No. 25, 26, & 27)

Western hostel no 25 plaster primer painting

• Painting of trusses completed for hostel NO.25
• Painting of internal wall in progress at hostel NO.25
• Preparation for pointing & foundation plaster in progress for hostel NO.25

Eastern Hostels (No. 28 & 29)

Aerial view for western hostels

• Painting of trusses in progress for hostel NO.28
• Preparation for pointing in progress at hostel No. 28
• Window seals installation & external plaster complete for hostel No. 28
• Internal wall plastering complete at hostel NO.29

Library

Roofing continues at library

• Painting of trusses continues
• Roofing in progress

Teachers and Headmaster's House

Foundation plaster in progress

• Ceiling board installation complete for teachers house NO. 15 to 20
• Blundering continues for house number 21
• Foundation plaster in progress for house NO. 15 to 21 in progress
• Painting of internal walls for head masters house in progress
• Preparation for painting for house NO. 15 to 21 in progress
• Screed floor to commence soon for house NO. 16 to 21

Cafeteria

Aerial view for cafeteria

• Screed floor completed
• Foundation plaster in progress
• Storm water drainage system to commence
• Foul drainage system completed

Staff Houses

Aerial view for staff houses

• Ceiling board painting in progress
• Fitting for Kitchen sink basin to commence soon
• Foundation plaster completed
• Preparation for storm water drainage in progress

Western and Eastern Ablution blocks

Western ablution pointing in progress

• Internal & external wall plaster finishes continues
• Pointing of external walls in progress
• Preparation for foundation plaster to commence soon

Rectory Extensions

Rectory substructure completed

• Block work for perimeter wall complete
• Slab casting completed.
• Preparation for superstructure block-work in progress

Convent

Ground view for convent substructure

• Footing casting in progress
• Block work in progress

Conversion of office to apartment

Footing casting completed

• Footing casting completed
• Preparation for block-work in progress

Playing Fields

Excavation for playing fields completed

• Excavation for playing fields completed


Other Works

External Works
– Septic tank: Tank 1 & 2

* All remaining activities to resume soon
* Construction of soak way pit to commence soon

Sewer drainage system by sub-contractor 94%
* The sewer line system installation, including all piping completed
* Manholes construction in progress

– Earth works (75%)
* Road reshaping & gravel level refill to resume soon (delayed due to rains)
* Crusher run final finish pending

Electrical and Plumbing First and Second Phase Activities in progress (subcontractor)

Other Pictures

Site aerial view

###
end update

Meet Our Student Communications Team

As part of sharing the journey and stories of Our Lady of Namlenga High School, six students have been chosen to help write and communicate about life at the school. With their help, people from all over the world can get to know the students, teachers, and faculty that make up Our Lady of Namlenga. […]

Read More

Progress Report – December 5, 2025

Work progresses as our completion dates nears. […]

Read More

Progress Report – September 30, 2025

Work progresses as our completion dates nears. […]

Read More

Site Plan – October 08, 2025

Work progresses as our completion dates nears. […]

Read More

Progress Report – August 1, 2025

Work progresses as our completion dates nears. […]

Read More

Progress Report – June 20, 2025

Work moving along steadily as we work toward completion. […]

Read More

Progress Report – June 5, 2025

Work continues as we aim to finish by the end of Summer. […]

Read More

Progress Report – May 23, 2025

Work continues as we progress toward our completion date. […]

Read More

Progress Report – May 9, 2025

Work will continue through the summer with a new completion date of August 31, 2025. […]

Read More

Progress Report – April 11, 2025

Progress continues as we work toward a completion date of April 30, 2025. […]

Read More