Updated June 10, 2025

Client: The Archdiocese of Blantyre
Consultant: Team Lift Inc. / Hagios Consulting Engineers
Contractor: Sitbec Ltd.

Proposed Contract Period: 80 weeks
Proposed Time Extension:  141 weeks
Proposed Commencement Date: January 2, 2023
Proposed Completion Date: December 31, 2024
Revised Completion Date: August 31, 2025
Time Elapsed: 128 weeks
Revised Elapsed Time Percentage: 90.8%
Overall Progress Percentage: 89.5%

Class Blocks (4 No)

Western teaching area section

• Storm water drainage in progress at western section
• Landscaping continues at western section

Pavilion (4 No)

Superstructure block-work for pavilion NO.12 continues

• Blackboard installation complete for pavilion NO.7
• Block-work for pavilion NO.12 at ring beam level

Laboratory (2 No)

Storm water drainage construction at western laboratory

Western and Eastern Laboratory

• Terrazzo polishing to resume soon
• Painting of external and internal walls continues
• Storm water drainage continues

Administration

External view for administration

• Internal and external wall paintings complete
• Installation of plumbing fittings to resume soon
• Door fitting continues

Multipurpose

Aerial view for multipurpose hall

• Veranda skirting continues
• Landscaping in progress

Western Hostels (No. 25)

Western hostel no 25 plaster primer painting

• Painting of internal wall (delayed due to revision in the paint selection)
• Preparation for pointing & foundation plaster in progress

Eastern Hostels (No. 28)

Aerial view for western hostels

• Painting of trusses complete
• Preparation for external and internal wall painting underway
• Screed floor preparation for storage and washing area underway
• Pointing complete
• Window sills installation & external plaster complete
• Preparation for foundation plaster in progress

Library

Roofing continues at library

• Painting of trusses continues
• Roofing continues

Teachers and Headmaster's House

Screed floor at teachers house no.19

• Ceiling board installation complete for teachers house NO. 15 to 20
• Brandering continues for house number 21
• Foundation plaster in progress for house NO. 15 to 21
• Painting of internal & external walls for head masters house in progress
• Door fitting for headmasters house in progress
• Painting of external walls continues for house NO.15 to 21
• Screed floor 80% complete for house NO. 16 to 21

Cafeteria

Aerial view for cafeteria

• Preparation for painting in progress
• Reveals almost 90% complete
• Storm water drainage system to commence

Staff Houses

Aerial view for staff houses

• Ceiling board painting continues
• Preparation for external and internal wall continues
• Door fitting to commence soon
• Preparation for storm water drainage in progress

Western and Eastern Ablution blocks

Western ablution pointing in progress

• Pointing of ablution NO. 35 completed
• Pointing in progress for ablution NO. 36
• Foundation plaster to commence soon for ablution 36
• Internal and external plaster completed for ablution NO. 37 & 38
• Pointing to commence soon for ablution NO.37 & 38


Other Works

External Works
– Septic tank: Tank 1 & 2

* All remaining activities to resume soon
* Construction of soak way pit to commence soon

Sewer drainage system by sub-contractor 94%
* The sewer line system installation, including all piping completed
* Manholes construction in progress

– Earth works (75%)
* Road reshaping & gravel level refill to resume soon (delayed due to rains)
* Crusher run final finish pending

Electrical and Plumbing First and Second Phase Activities in progress (subcontractor)

Other Pictures

Site aerial view

###
end update

Meet Our Student Communications Team

As part of sharing the journey and stories of Our Lady of Namlenga High School, six students have been chosen to help write and communicate about life at the school. With their help, people from all over the world can get to know the students, teachers, and faculty that make up Our Lady of Namlenga. […]

Read More

Progress Report – December 5, 2025

Work progresses as our completion dates nears. […]

Read More

Progress Report – September 30, 2025

Work progresses as our completion dates nears. […]

Read More

Site Plan – October 08, 2025

Work progresses as our completion dates nears. […]

Read More

Progress Report – August 1, 2025

Work progresses as our completion dates nears. […]

Read More

Progress Report – June 20, 2025

Work moving along steadily as we work toward completion. […]

Read More

Progress Report – May 30, 2025

With the main buildings close to completion, efforts turn toward completing the rectory and playing fields. […]

Read More

Progress Report – May 23, 2025

Work continues as we progress toward our completion date. […]

Read More

Progress Report – May 9, 2025

Work will continue through the summer with a new completion date of August 31, 2025. […]

Read More

Progress Report – April 11, 2025

Progress continues as we work toward a completion date of April 30, 2025. […]

Read More