Updated June 25, 2025

Client: The Archdiocese of Blantyre
Consultant: Team Lift Inc. / Hagios Consulting Engineers
Contractor: Sitbec Ltd.

Proposed Contract Period: 80 weeks
Proposed Time Extension:  141 weeks
Proposed Commencement Date: January 2, 2023
Proposed Completion Date: December 31, 2024
Revised Completion Date: August 31, 2025
Time Elapsed: 130 weeks
Revised Elapsed Time Percentage: 92.2%
Overall Progress Percentage: 90%

Class Blocks (4 No)

Eastern teaching area section

• Storm water drainage in progress at western section
• Landscaping continues at western section
• Painting of blackboards in progress for all classes
• Construction of ramps and steps in progress

Pavilion (4 No)

Beam filling for pavilion NO.12 in progress

Eastern & Western Pavilions
• Windowsills and beam jointing for pavilion NO.7 complete
• Beam filling and plaster in progress for pavilion NO.12
• Beam reveals for pavilion NO.12 in progress
• Lime putty in progress for pavilion NO.6

Laboratory (2 No)

Steps and ramps construction in progress

Western and Eastern Laboratory
• Terrazzo polishing in progress
• Ramps and step construction in progress

Administration

External view for administration

• Steps and ramps construction in progress
• Installation of plumbing fittings in progress
• Door fitting continues

Clocktower

Clocktower plastering and pointing in progress

• Lime putty complete
• Painting of trusses in progress
• External wall plaster and pointing in progress

Multipurpose

Aerial view for multipurpose hall

• Ramps and steps construction in progress
• Walkway pavement preparation in progress

Western Hostels (No. 25)

Western hostel painting in progress

• Painting of internal walls continues
• Foundation plaster in progress
• Window reveals complete
• Screed floor for laundry and stores complete
• Door fixing and plumbing fitting to resume soon

Eastern Hostels (No. 28)

Aerial view for western hostel

• External and internal wall painting in progress
• Screed floor preparation for storage and washing complete
• Beam and window reveals complete
• Foundation plaster complete
• Preparation for storm water drainage underway

Library

Roofing continues at library

• Painting of trusses continues
• Roofing continues
• Beam filling, foundation plaster and pointing underway

Teachers and Headmaster's House

Painting for teachers house NO.16

• Ceiling board installation complete for teachers houses
• Foundation plaster complete for house NO. 15 to 21
• Painting of internal & external walls for house NO.15 to 21 in progress
• Door fitting for house NO.15 to 21 in progress
• Screed floor complete for house NO. 15 to 21
• Preparation for storm water drainage underway1

Cafeteria

Aerial view for cafeteria

• Preparation for painting in progress
• Reveals complete
• Storm water drainage system to commence soon

Staff Houses

Aerial view for staff houses

• Door fitting in progress
• Preparation for storm water drainage in progress

Western and Eastern Ablution blocks

Western ablution pointing in progress

• Pointing of all ablution complete
• Foundation plaster complete for all ablutions
• Preparation for screed floor in progress for ablution NO.36 and 37 in progr
• Preparation for partition wall in progress


Other Works

External Works
– Septic tank: Tank 1 & 2

* All remaining activities to resume soon
* Construction of soak way pit to commence soon

Sewer drainage system by sub-contractor 94%
* The sewer line system installation, including all piping completed
* Manholes construction in progress

– Earth works (75%)
* Road reshaping & gravel level refill to resume soon (delayed due to rains)
* Crusher run final finish pending

Electrical and Plumbing First and Second Phase Activities in progress (subcontractor)

Other Pictures

Site aerial view

###
end update

Meet Our Student Communications Team

As part of sharing the journey and stories of Our Lady of Namlenga High School, six students have been chosen to help write and communicate about life at the school. With their help, people from all over the world can get to know the students, teachers, and faculty that make up Our Lady of Namlenga. […]

Read More

Progress Report – December 5, 2025

Work progresses as our completion dates nears. […]

Read More

Progress Report – September 30, 2025

Work progresses as our completion dates nears. […]

Read More

Site Plan – October 08, 2025

Work progresses as our completion dates nears. […]

Read More

Progress Report – August 1, 2025

Work progresses as our completion dates nears. […]

Read More

Progress Report – June 5, 2025

Work continues as we aim to finish by the end of Summer. […]

Read More

Progress Report – May 30, 2025

With the main buildings close to completion, efforts turn toward completing the rectory and playing fields. […]

Read More

Progress Report – May 23, 2025

Work continues as we progress toward our completion date. […]

Read More

Progress Report – May 9, 2025

Work will continue through the summer with a new completion date of August 31, 2025. […]

Read More

Progress Report – April 11, 2025

Progress continues as we work toward a completion date of April 30, 2025. […]

Read More