Updated June 25, 2025

Client: The Archdiocese of Blantyre
Consultant: Team Lift Inc. / Hagios Consulting Engineers
Contractor: Sitbec Ltd.

Proposed Contract Period: 80 weeks
Proposed Time Extension:  141 weeks
Proposed Commencement Date: January 2, 2023
Proposed Completion Date: December 31, 2024
Revised Completion Date: August 31, 2025
Time Elapsed: 130 weeks
Revised Elapsed Time Percentage: 92.2%
Overall Progress Percentage: 90%

Class Blocks (4 No)

Eastern teaching area section

• Storm water drainage in progress at western section
• Landscaping continues at western section
• Painting of blackboards in progress for all classes
• Construction of ramps and steps in progress

Pavilion (4 No)

Beam filling for pavilion NO.12 in progress

Eastern & Western Pavilions
• Windowsills and beam jointing for pavilion NO.7 complete
• Beam filling and plaster in progress for pavilion NO.12
• Beam reveals for pavilion NO.12 in progress
• Lime putty in progress for pavilion NO.6

Laboratory (2 No)

Steps and ramps construction in progress

Western and Eastern Laboratory
• Terrazzo polishing in progress
• Ramps and step construction in progress

Administration

External view for administration

• Steps and ramps construction in progress
• Installation of plumbing fittings in progress
• Door fitting continues

Clocktower

Clocktower plastering and pointing in progress

• Lime putty complete
• Painting of trusses in progress
• External wall plaster and pointing in progress

Multipurpose

Aerial view for multipurpose hall

• Ramps and steps construction in progress
• Walkway pavement preparation in progress

Western Hostels (No. 25)

Western hostel painting in progress

• Painting of internal walls continues
• Foundation plaster in progress
• Window reveals complete
• Screed floor for laundry and stores complete
• Door fixing and plumbing fitting to resume soon

Eastern Hostels (No. 28)

Aerial view for western hostel

• External and internal wall painting in progress
• Screed floor preparation for storage and washing complete
• Beam and window reveals complete
• Foundation plaster complete
• Preparation for storm water drainage underway

Library

Roofing continues at library

• Painting of trusses continues
• Roofing continues
• Beam filling, foundation plaster and pointing underway

Teachers and Headmaster's House

Painting for teachers house NO.16

• Ceiling board installation complete for teachers houses
• Foundation plaster complete for house NO. 15 to 21
• Painting of internal & external walls for house NO.15 to 21 in progress
• Door fitting for house NO.15 to 21 in progress
• Screed floor complete for house NO. 15 to 21
• Preparation for storm water drainage underway1

Cafeteria

Aerial view for cafeteria

• Preparation for painting in progress
• Reveals complete
• Storm water drainage system to commence soon

Staff Houses

Aerial view for staff houses

• Door fitting in progress
• Preparation for storm water drainage in progress

Western and Eastern Ablution blocks

Western ablution pointing in progress

• Pointing of all ablution complete
• Foundation plaster complete for all ablutions
• Preparation for screed floor in progress for ablution NO.36 and 37 in progr
• Preparation for partition wall in progress


Other Works

External Works
– Septic tank: Tank 1 & 2

* All remaining activities to resume soon
* Construction of soak way pit to commence soon

Sewer drainage system by sub-contractor 94%
* The sewer line system installation, including all piping completed
* Manholes construction in progress

– Earth works (75%)
* Road reshaping & gravel level refill to resume soon (delayed due to rains)
* Crusher run final finish pending

Electrical and Plumbing First and Second Phase Activities in progress (subcontractor)

Other Pictures

Site aerial view

###
end update

Progress Report – December 5, 2025

Work progresses as our completion dates nears. […]

Read More

Progress Report – September 30, 2025

Work progresses as our completion dates nears. […]

Read More

Site Plan – October 08, 2025

Work progresses as our completion dates nears. […]

Read More

Progress Report – August 1, 2025

Work progresses as our completion dates nears. […]

Read More

Progress Report – June 5, 2025

Work continues as we aim to finish by the end of Summer. […]

Read More

Progress Report – May 30, 2025

With the main buildings close to completion, efforts turn toward completing the rectory and playing fields. […]

Read More

Progress Report – May 23, 2025

Work continues as we progress toward our completion date. […]

Read More

Progress Report – May 9, 2025

Work will continue through the summer with a new completion date of August 31, 2025. […]

Read More

Progress Report – April 11, 2025

Progress continues as we work toward a completion date of April 30, 2025. […]

Read More

Progress Report – March 28, 2025

We’re in the home stretch! Aiming for a completion date of April 30, 2025. […]