Updated June 10, 2025
Client: The Archdiocese of Blantyre
Consultant: Team Lift Inc. / Hagios Consulting Engineers
Contractor: Sitbec Ltd.
Proposed Contract Period: 80 weeks
Proposed Time Extension:Â 141 weeks
Proposed Commencement Date: January 2, 2023
Proposed Completion Date: December 31, 2024
Revised Completion Date: August 31, 2025
Time Elapsed: 128 weeks
Revised Elapsed Time Percentage: 90.8%
Overall Progress Percentage: 89.5%
Class Blocks (4 No)

• Storm water drainage in progress at western section
• Landscaping continues at western section
Pavilion (4 No)

• Blackboard installation complete for pavilion NO.7
• Block-work for pavilion NO.12 at ring beam level
Laboratory (2 No)

Western and Eastern Laboratory
• Terrazzo polishing to resume soon
• Painting of external and internal walls continues
• Storm water drainage continues
Administration

• Internal and external wall paintings complete
• Installation of plumbing fittings to resume soon
• Door fitting continues
Multipurpose

• Veranda skirting continues
• Landscaping in progress
Western Hostels (No. 25)

• Painting of internal wall (delayed due to revision in the paint selection)
• Preparation for pointing & foundation plaster in progress
Eastern Hostels (No. 28)

• Painting of trusses complete
• Preparation for external and internal wall painting underway
• Screed floor preparation for storage and washing area underway
• Pointing complete
• Window sills installation & external plaster complete
• Preparation for foundation plaster in progress
Library

• Painting of trusses continues
• Roofing continues
Teachers and Headmaster's House

• Ceiling board installation complete for teachers house NO. 15 to 20
• Brandering continues for house number 21
• Foundation plaster in progress for house NO. 15 to 21
• Painting of internal & external walls for head masters house in progress
• Door fitting for headmasters house in progress
• Painting of external walls continues for house NO.15 to 21
• Screed floor 80% complete for house NO. 16 to 21
Cafeteria

• Preparation for painting in progress
• Reveals almost 90% complete
• Storm water drainage system to commence
Staff Houses

• Ceiling board painting continues
• Preparation for external and internal wall continues
• Door fitting to commence soon
• Preparation for storm water drainage in progress
Western and Eastern Ablution blocks

• Pointing of ablution NO. 35 completed
• Pointing in progress for ablution NO. 36
• Foundation plaster to commence soon for ablution 36
• Internal and external plaster completed for ablution NO. 37 & 38
• Pointing to commence soon for ablution NO.37 & 38
Other Works
External Works
– Septic tank: Tank 1 & 2
* All remaining activities to resume soon
* Construction of soak way pit to commence soon
Sewer drainage system by sub-contractor 94%
* The sewer line system installation, including all piping completed
* Manholes construction in progress
– Earth works (75%)
* Road reshaping & gravel level refill to resume soon (delayed due to rains)
* Crusher run final finish pending
Electrical and Plumbing First and Second Phase Activities in progress (subcontractor)
Other Pictures















###
end update