Updated August 20, 2024
Client: The Archdiocese of Blantyre
Consultant: Team Lift Inc. / Hagios Consulting Engineers
Contractor: Sitbec Ltd.
Proposed Contract Period: 80 weeks
Proposed Time Extension:Â 9 weeks
Proposed Commencement Date: January 2, 2023
Proposed Completion Date: July 2, 2024
Revised Completion Date: August 31, 2024
Time Elapsed: 84 weeks
Elapsed Time Percentage: 105%
Revised Elapsed Time Percentage: 94%
Overall Progress Percentage: 81%
AUGUST TARGETS:
– Finalizing fixing of steel roof trusses and iron sheets
– Finalizing window and door frames fixing
– Superstructure wall finishes continues
– Earth works and other external works continue
Pictures of work in progress can be see below.
Administration Block
Multipurpose Hall
Classrooms (2No)
Pavillions (2 No)
Laboratory (1 No)
Library
Staff Housing
Hostels (2 No)
Headmaster and Teachers' Housing
Cafeteria
Other Works
Fixing of trusses, iron sheets, door & window frames in progress
Ablution Blocks & Clock tower
– superstructure activities in progress (1st ablution block)
– substructure activities in progress (2nd ablution block)
– superstructure activities in progress (clocktower)
External Works
– Septic tank
* Wall plastering (1st tank)
* Trench cleaning and setting out (2nd tank)
– Road network & Carparks
* soil cutting
* road formation, soil clarification, mixing, and compaction
* subbase layer gravel filling
* gravel hauling in progress
Electrical and Plumbing First Phase Activities in Progress
Other Pictures
###
end update