Updated August 27, 2024

Client: The Archdiocese of Blantyre
Consultant: Team Lift Inc. / Hagios Consulting Engineers
Contractor: Sitbec Ltd.

Proposed Contract Period: 80 weeks
Proposed Time Extension:  9 weeks
Proposed Commencement Date: January 2, 2023
Proposed Completion Date: July 2, 2024
Revised Completion Date: August 31, 2024
Time Elapsed: 85 weeks
Elapsed Time Percentage: 106%
Revised Elapsed Time Percentage: 95%
Overall Progress Percentage: 82%

AUGUST TARGETS:

– Finalizing fixing of steel roof trusses and iron sheets
– Finalizing window and door frames fixing
– Superstructure wall finishes continues
– Earth works and other external works continue

Pictures of work in progress can be see below.

Administration Block

WALL FINISHES & ROOFING Wall finishes 90% Iron sheet fixing 99%

Multipurpose Hall

ROOFING AND WALL FINISHES wall finishes in progress Iron sheet fixing 98%

Classrooms (2No)

ROOFING & WALL FINISHES Wall finishes 97% Door & window frame fixing 100% Fixing of iron sheets 98%

Pavillions (2 No)

ROOFING & WALL FINISHES Fabrication of trusses 100% Truss fixing 20% Wall finishes 15%

Laboratory (1 No)

ROOFING AND WALL FINISHES Inside room sink slab activities 70% wall finishes 98% Iron sheet fixing 98%

Library

ROOFING AND WALL FINISHES Truss fabrication 97% Truss fixing 15% Door and window frames fixing 100% Wall finishes 50 %

Staff Housing

ROOFING AND WALL FINISHES Wall finishes 60% Door & window frame fixing 95% Iron sheet fixing 98%

Hostels (2 No)

TRUSSES AND WALL FINISHES wall finishes in progress Door & window frame fixing 70% Truss fabrication 100% Truss fixing 95%

Headmaster and Teachers' Housing

ROOFING AND WALL FINISHES Wall finishes & beam filling 60% Door & window frame fixing 98% Truss fixing 90% 1.9

Cafeteria

ROOFING AND WALL FINISHES Wall finishes 60% Door & window frames fixing 95% Iron sheet fixing 98%

Other Works

Fixing of trusses, iron sheets, door & window frames in progress

trusses
door and window frames

Ablution Blocks & Clock tower
– superstructure activities in progress (1st ablution block)
– substructure activities in progress (2nd ablution block)
– superstructure activities in progress (clocktower)

ablution blocks
clocktower

External Works
– Septic tank

* Wall plastering (1st tank)
* Trench cleaning and setting out (2nd tank)

– Road network & Carparks
* soil cutting
* road formation, soil clarification, mixing, and compaction
* subbase layer gravel filling
* gravel hauling in progress

wall plastering
trench cleaning

Electrical and Plumbing First Phase Activities in Progress

Other Pictures

site plan view
site centre plan view
site plan view
classroom inside lime putty finishes
iron sheets on site
septic tank
staff house wall finishes

###
end update

Progress Report – October 25, 2024

Work continues, moving toward targets. […]

Read More

Progress Report – October 11, 2024

New targets set for month of October. […]

Read More

Progress Report – September 12, 2024

New completion date has been set; work continues. […]

Read More

Progress Report – August 16, 2024

Progress continues. […]

Read More

Progress Report – July 26, 2024

New targets set for August. […]

Read More

Progress Report – July 12, 2024

Work continues on track. […]

Read More

Progress Report – June 21, 2024

Overall progress on project is at 79%. […]

Read More

Progress Report – June 14, 2024

Progress continues on June targets. […]

Read More

Progress Report – May 31, 2024

Progress continues with new June targets established. […]

Read More

Progress Report – May 17, 2024

Overall completion percentage at 74.5%. […]