Updated December 10, 2024
Client: The Archdiocese of Blantyre
Consultant: Team Lift Inc. / Hagios Consulting Engineers
Contractor: Sitbec Ltd.
Proposed Contract Period: 80 weeks
Proposed Time Extension:Â 26 weeks
Proposed Commencement Date: January 2, 2023
Proposed Completion Date: July 2, 2024
Revised Completion Date: December 31, 2024
Time Elapsed: 97 weeks
Revised Elapsed Time Percentage: 91.5%
Overall Progress Percentage: 84.5%
NOVEMBER TARGETS:
CONTINOUS FIXING OF TRUSSES AND IRON SHEET FOR THE REMAINING 2 PAVILIONS, LIBRARY, ABLUTION BLOCKS & 4 HOSTELS
ONGOING FORMWORK PREPARATION, STEEL BENDING & FIXING FOR THE SEPTIC TANK SLABS
CEILING BLUNDERING INSTALLATION FOR STAFF HOUSES IN PROGRESS
SUPERSTRUCTURE EXTERNAL & INTERNAL WALL FINISHES FOR ALL STRUCTURES CONTINUES
EXCAVATING, LEVELING , AND PIPE FIXING FOR THE SEWER DRAINAGE SYSTEMÂ CONTINUES
INTRODUCING SITE FOUL WATER DRAINAGE SYSTEM
CONSTRUCTION OF THE LIBRARY CONCRETE BLOCK TRACES & RAMPS IS ONGOING
ELECTRICAL AND PLUMBING WORKS FOR ALL STRUCTURES CONTINUES
1.1 HOSTELS (6No)

1.2 Class Blocks (4No)

1.3 PAVILION (4NO)

1.4 LABORATORY (2NO)

LIBRARY

ABLUTION BLOCK 4NO

CLOCKTOWER 1NO & ADMINISTRATION

MULTIPURPOSE HALL, TEACHERS, & HEAD MASTERS HOUSE

CAFETERIA & STAFF HOUSES

Other Works
External Works
– Septic tank
Tank 1 & 2
* Top cover concrete casting activities continues
Sewer drainage system 40%
* Setting out, excavation, cleaning, sand level checking, pipe fixing & sand & soil back filling
– Earth works 95%
* crusher run final finish pending
-Site road temporary drains 40%
Electrical and plumbing first phase activities in progress
Other Pictures








###
end update