Updated December 5, 2023

Concrete slab casting started on some structures like the administration block and classroom blocks. Hostels and cafeteria foundation block work is at an advanced stage. We are racing against time to complete all substructure works before Christmas close down on 22nd December 2023. In maintaining the foundation levels well above the ground, our foundations blockwork are higher than normal averaging 1200mm high. The resultant extra block work and backfilling and compaction has led to completing the substructure works with the onset of rainy season.

Our team of young engineers (e.g. Tusayiwe and Chifundo) have been tasked to work on the drainage designs to meet international standards. They have assured me that they will come up with an acceptable layout to take care of the runoff on the site.

Pictures of ongoing construction work can be seen below.

Administration Block

Concrete slab is 100% complete; Curing in progress.

Multipurpose Hall

Electrical service installation in progress; ready for in situ concrete slab

Classrooms (4No)

Concrete slab casted for 2No. The remaining 2 are ready for concrete as well.

Pavillions (4 No)

Slab concrete casting in progress - 35%

Laboratory (2 No)

Ready for concrete

Library

Gravel backfill and ground beams form; work in progress

Staff Housing (3 No)

Gravel backfilling 80% complete; ready for concrete slab next week

Hostels (6 No)

Foundation blockwork 95%; last wing of the last hostel remaining

Headmaster and Teachers' Housing

Block soil and gravel backfilling continues

Cafeteria

Foundation wall blockwork (98%)

Other Works

1. Block Moulding
11,200 blocks
Installation of third block-making machine completed

2. Road Maintenance
Outside site road grading and gravel filling

Other Pictures

Healthy & Safety

Site Accidents = 8 different cases, 7 recovered.
All 8 cases were reported and recorded.

Theft incidents = 0

Construction Materials

Material quantities and their sources
Cement = 1150 pockets
Sand = 1240 tones
Quarry = 2150 tones
60m mesh wire = 50 rolls

FUEL SUPPLIER AND LOCATION
– Nkando ENGEN filling station, Mulanje (7km from Namulenga site)

CEMENT SUPPLIER AND LOCATION
– CPL Cement Company, Mangochi

QUARRY AND SAND
– Namulenga river in Mulanje (11km)
– Quarry: Njuli Chiradzulu (79 km)

###
end update

Progress Report – December 5, 2025

Work progresses as our completion dates nears. […]

Read More

Progress Report – September 30, 2025

Work progresses as our completion dates nears. […]

Read More

Site Plan – October 08, 2025

Work progresses as our completion dates nears. […]

Read More

Progress Report – August 1, 2025

Work progresses as our completion dates nears. […]

Read More

Progress Report – June 20, 2025

Work moving along steadily as we work toward completion. […]

Read More

Progress Report – June 5, 2025

Work continues as we aim to finish by the end of Summer. […]

Read More

Progress Report – May 30, 2025

With the main buildings close to completion, efforts turn toward completing the rectory and playing fields. […]

Read More

Progress Report – May 23, 2025

Work continues as we progress toward our completion date. […]

Read More

Progress Report – May 9, 2025

Work will continue through the summer with a new completion date of August 31, 2025. […]

Read More

Progress Report – April 11, 2025

Progress continues as we work toward a completion date of April 30, 2025. […]