Updated December 9, 2025

Client: The Archdiocese of Blantyre
Consultant: Team Lift Inc. / Hagios Consulting Engineers
Contractor: Sitbec Ltd.

Proposed Contract Period: 80 weeks
Proposed Time Extension:  141 weeks
Proposed Commencement Date: January 2, 2023
Proposed Completion Date: December 31, 2024
Revised Completion Date: August 31, 2025
Time Elapsed: 141 weeks
Revised Elapsed Time Percentage: 100%
Overall Progress Percentage: 97%

Western and Eastern Teaching Area section
  • Fascia boards installation to resume soon
  • Preparations for road side drains in progress
Western Pavilion Class Section

Fascia boards installation to resume soon

Eastern Laboratory Section
  • Paved walk ways connecting Eastern classes on hold
  • Installation of underground cables for ESCOM electricity completed
Aerial View of Administration
Aerial View of Multipurpose Hall
  • The hall is completed and operational, pending ESCOM Electricity connection
  • Installation of underground cables for ESCOM electricity in progress
Aerial view of Hostel No. 25
  • Girls Hostel 1 is complete and operational.
  • Installation of underground cables for ESCOM electricity complete
Aerial view of Western Hostels

Internal plaster for Hostel completed.
Wiring for both hostels completed
Installation of underground cables for ESCOM electricity complete in hostel no.27
Landscaping around the hostels in progress
Water Trough and Hand Wash Basin installation/casting in progress.
Fascia dots and other preparations for floor screed complete in hostel no.27
Entrance & wall top reveals and internal air-vents installation in progress in no.26
Window sills finishing completed in hostel no. 27 and in progress in no.26

Aerial view of Eastern Hostel No.28
  • The hostel is complete and operational.
  • Installation of underground cables for ESCOM electricity complete
Eastern Hostels Aerial View

External plaster complete in all hostels
Internal plaster in progress (95%) for Hostel no.30 wing A
Lime putty in hostel no.29 completed
Water trough installation complete for hostel no.29
Casting hand wash basins complete for hostel no.30, in progress in no.29
Preparations for floor screed in progress in both hostels
Plumbing fittings and installations still in progress for both Hostels
Wash-trough installation preparation in progress in both hostels
Foundation plaster in progress for hostel no.30
Internal Air-vents and entrance reveals complete in no.29 and in progress in no.30
Installation of underground cables for ESCOM electricity complete

Library Aerial and interior Views
Aerial view for teachers houses
Aerial photo of the sister’s Convent Building

Hand rails installation to resume soon.
All construction and fitting are complete and operational
Installation of underground cables for ESCOM electricity complete

Aerial view for teachers houses

All facilities and fittings complete and operational.
Preparation for storm-water drain at the car park in progress
Roof Gutters installation in progress
Pending ESCOM electricity connection

Aerial photo of the sister’s Convent Building
  • Superstructure Block work in progress
  • Ring beam formwork in progress
Aerial photo of Rectory Building.
  • Block work to beam level complete
  • Ring beam formwork and casting in progress
Aerial photo of cafeteria
Interior photo of cafeteria
  • All construction and fittings are complete and operational.
  • Installation of underground cables for ESCOM electricity complete
Aerial View for Staff Houses
  • Preparations for Storm water drain construction in progress
  • All other construction and fittings are complete and operational
  • Pending ESCOM electricity connection.
Eastern Ablution Aerial View
  • Cleaning around ablutions completed
  • All Ablutions are complete and operational, pending lights connection
  • Construction of manholes for electrical cable line in progress

Other Works

External Works
– Septic tank: Tank 1, 2, and 3

* Slab casting for cafeteria septic tank complete
* Soak way pit 1,2 and 3 complete

Sewer drainage system by sub-contractor 100%
* The sewer line system installation, including all piping completed
* Manholes construction in progress
* Construction of Manholes for underground electrical cables in progress

Earth works (75%)
* road reshaping & gravel level refill to resume soon
* crushed stone road base finish pending

Incinerator, Water tank stand & Pit-latrines
* Door fittings in all pit-latrines complete
* Incinerator construction complete
* Pointing and floor at western Pit latrine near Ablution 2 in progress

Electrical and Plumbing First and Second Phase Activities in progress (subcontractor)

Challenges
* We are still experiencing intensifying rains which are delaying our progress in general

###
end update

Progress Report – September 30, 2025

Work progresses as our completion dates nears. […]

Read More

Site Plan – October 08, 2025

Work progresses as our completion dates nears. […]

Read More

Progress Report – August 1, 2025

Work progresses as our completion dates nears. […]

Read More

Progress Report – June 20, 2025

Work moving along steadily as we work toward completion. […]

Read More

Progress Report – June 5, 2025

Work continues as we aim to finish by the end of Summer. […]

Read More

Progress Report – May 30, 2025

With the main buildings close to completion, efforts turn toward completing the rectory and playing fields. […]

Read More

Progress Report – May 23, 2025

Work continues as we progress toward our completion date. […]

Read More

Progress Report – May 9, 2025

Work will continue through the summer with a new completion date of August 31, 2025. […]

Read More

Progress Report – April 11, 2025

Progress continues as we work toward a completion date of April 30, 2025. […]

Read More

Progress Report – March 28, 2025

We’re in the home stretch! Aiming for a completion date of April 30, 2025. […]

Read More

HELP US

REACH OUR GOAL!

Working to complete Our Lady of Namulenga High School