Updated March 3, 2025
Client: The Archdiocese of Blantyre
Consultant: Team Lift Inc. / Hagios Consulting Engineers
Contractor: Sitbec Ltd.
Proposed Contract Period: 80 weeks
Proposed Time Extension:Â 123 weeks
Proposed Commencement Date: January 2, 2023
Proposed Completion Date: December 31, 2024
Revised Completion Date: April 30, 2025
Time Elapsed: 114 weeks
Revised Elapsed Time Percentage: 93%
Overall Progress Percentage: 89%
EXECUTIVE SUMMARY:
- TEACHING AREA: Multipurpose Hall, Classroom Blocks, Laboratory Blocks, and Pavilions plus Ablution Blocks – Will be handed over for Furniture Fittings on 23rd Feb 2025.
- HOSTELS: First 2 Hostels, 1 for boys and 1 for Girls will be ready for receiving Beds on 09th March 2025 and the other 4 Hotels will be ready on 30th April 2025.
- HEAD & TEACHERS HOUSES: Will be ready for occupation on 23rd March 2025.
- STAFF HOUSES: All 3 semi-detached will be ready for occupation on 6th April 2025.
- CAFETERIA & LIBRARY: Will be ready on 13th April 2025
- EXTERNAL WORKS: Recreational Facilities i.e. all grounds, Electrical and Plumbing works for all structures continues
NOTE:
We have shifted our main focus from the teaching area to the headmaster’s house and two hostels. However, we still have some outstanding work on the pavilions, which have been converted into classroom blocks. Additionally, there are critical tasks remaining in the teaching area that require more attention to ensure quality is maintained. These works are still in progress. As of now, we have reached 95% completion in this section.
Class Blocks (4 No)

Pavilion (4 No)

Laboratory (4 No)

Administration

Multipurpose

Hostels (4No)

Library

Ablution Block (4 No)

Teachers & Headmaster House

Cafeteria & Staff Houses
Cafeteria: Painting in progress; ready for glazing
Staff houses: read for ceiling board installation.
Other Works
External Works
– Septic tank
* Tanks 1 & 2: remaining activities to follow the summary
Sewer drainage system (western section 98%)
* Setting out, excavation, cleaning, sand level checking, pipe fixing & sand &
soil back filling, construction of manholes
– Earth works (95%)
* Crusher run final finish pending
* Football pitch and coats clearing preparations on going
Electrical and Plumbing First and Second Phase Activities in progress (subcontractor)
Electrical and Plumbing Works:
First-phase activities in progress across all structures.
Other Pictures












###
end update