Updated January 21, 2025

Client: The Archdiocese of Blantyre
Consultant: Team Lift Inc. / Hagios Consulting Engineers
Contractor: Sitbec Ltd.

Proposed Contract Period: 80 weeks
Proposed Time Extension:  26 weeks
Proposed Commencement Date: January 2, 2023
Proposed Completion Date: July 2, 2024
Revised Completion Date: December 31, 2024
Time Elapsed: 104 weeks
Revised Elapsed Time Percentage: 88%
Overall Progress Percentage: 88.6%

JANUARY ACTIVITIES:
General Site Works

  • Continuous fixing of trusses and iron sheets for the remaining library, ablution blocks and 4 hostels.
  • Ongoing formwork preparation, steel bending, and fixing and concrete casting for the septic tank slabs.
  • Ceiling blundering installation for staff and teachers’ houses.
  • Superstructure external and internal wall finishes for all structures.
  • Excavating, leveling, pipe fixing and construction of manholes for the site sewer drainage system.
  • Site foul water drainage system.
  • Electrical and plumbing works for all structures continue.

Progress continues steadily across all structures and external works. Major milestones for the next fortnight include completing septic tank tops, advancing site drainage systems, and finalizing trusses and iron sheets for key structures. Challenges such as material delivery delays and adverse weather conditions will require close monitoring.

Class Blocks (4 No)

WESTERN SECTION: Onging external and internal wall finishes; Foul water drains trench excavation. EASTERN SECTION: External and internal wall plaster primer painting in progress; finalizing window and beam reveals; floor screed casting, finishes, and curing.

Pavilion (4 No)

Converting pavilion block into a classroom block to resume. Floor screed preparations and wall finishes in progress (remaining pavilions.)

Laboratory (2 No)

WESTERN LABORATORY: Internal and external wall finishes continue. EASTERN LABORATORY: Plaster primer painting in progress; ready for floor screed casting.

Ablution Block (4 No)

Ongoing installation of timber trusses and iron sheets (two completed.) Internal and external wall finishes to resume.

Clocktower and Administration Block

CLOCKTOWER: Wall finishes to resume. ADMINISTRATION BLOCK: Plaster primer painting in progress; ready for ceiling board installation; ready for tiles fixing; foul drainage construction in progress.

Multipurpose Hall, Teachers' and Headmaster's Houses

Sewer drainage manholes blockwork in progress.

Cafeteria & Staff Houses

CAFETERIA: Ready for plaster primer painting; floor screed preparations. STAFF HOUSES: Ceiling blundering installation continues; ready for plaster primer painting.

Hostels (6 No)

Hostel 3 & 6: Truss installation done and now finalizing iron sheet fixing. Hostel 2 & 4: Truss installation and beam filling in progress. Hostel 1 & 4: Internal and external wall finishes to resume.

Other Works

External Works
– Septic tank
Tank 1 & 2

* Septic Tank 1 ready for slab casting

Sewer drainage system (58%)
* Activities include setting out, excavation, cleaning, sand level checking, pipe fixing, sand/soil backfilling, and manhole blockwork

– Earth works (95%)
* Crusher run final finish pending.

-Site roads
* Maintenance continues

Electrical and Plumbing Works:
First-phase activities in progress across all structures.

Other Pictures

Septic Tank 1 Top Cover ready for casting
Sewer Drainage Manholes Construction
Eastern section class blocks ongoing activities
Eastern section class blocks plaster primer painting
Administration office corridor walls painted with primer
Site plan
Installed Hostel sewer drainage pipes

###
end update

Progress Report – December 5, 2025

Work progresses as our completion dates nears. […]

Read More

Progress Report – September 30, 2025

Work progresses as our completion dates nears. […]

Read More

Site Plan – October 08, 2025

Work progresses as our completion dates nears. […]

Read More

Progress Report – August 1, 2025

Work progresses as our completion dates nears. […]

Read More

Progress Report – June 20, 2025

Work moving along steadily as we work toward completion. […]

Read More

Progress Report – June 5, 2025

Work continues as we aim to finish by the end of Summer. […]

Read More

Progress Report – May 30, 2025

With the main buildings close to completion, efforts turn toward completing the rectory and playing fields. […]

Read More

Progress Report – May 23, 2025

Work continues as we progress toward our completion date. […]

Read More

Progress Report – May 9, 2025

Work will continue through the summer with a new completion date of August 31, 2025. […]

Read More

Progress Report – April 11, 2025

Progress continues as we work toward a completion date of April 30, 2025. […]

Read More

HELP US

REACH OUR GOAL!

Working to complete Our Lady of Namulenga High School