Updated January 21, 2025
Client: The Archdiocese of Blantyre
Consultant: Team Lift Inc. / Hagios Consulting Engineers
Contractor: Sitbec Ltd.
Proposed Contract Period: 80 weeks
Proposed Time Extension:Â 26 weeks
Proposed Commencement Date: January 2, 2023
Proposed Completion Date: July 2, 2024
Revised Completion Date: December 31, 2024
Time Elapsed: 104 weeks
Revised Elapsed Time Percentage: 88%
Overall Progress Percentage: 88.6%
JANUARY ACTIVITIES:
General Site Works
- Continuous fixing of trusses and iron sheets for the remaining library, ablution blocks and 4 hostels.
- Ongoing formwork preparation, steel bending, and fixing and concrete casting for the septic tank slabs.
- Ceiling blundering installation for staff and teachers’ houses.
- Superstructure external and internal wall finishes for all structures.
- Excavating, leveling, pipe fixing and construction of manholes for the site sewer drainage system.
- Site foul water drainage system.
- Electrical and plumbing works for all structures continue.
Progress continues steadily across all structures and external works. Major milestones for the next fortnight include completing septic tank tops, advancing site drainage systems, and finalizing trusses and iron sheets for key structures. Challenges such as material delivery delays and adverse weather conditions will require close monitoring.
Class Blocks (4 No)

Pavilion (4 No)

Laboratory (2 No)

Ablution Block (4 No)

Clocktower and Administration Block

Multipurpose Hall, Teachers' and Headmaster's Houses

Cafeteria & Staff Houses

Hostels (6 No)

Other Works
External Works
– Septic tank
Tank 1 & 2
* Septic Tank 1 ready for slab casting
Sewer drainage system (58%)
* Activities include setting out, excavation, cleaning, sand level checking, pipe fixing, sand/soil backfilling, and manhole blockwork
– Earth works (95%)
* Crusher run final finish pending.
-Site roads
* Maintenance continues


Electrical and Plumbing Works:
First-phase activities in progress across all structures.
Other Pictures







###
end update