Updated January 29, 2024

Client: The Archdiocese of Blantyre
Consultant: Team Lift Inc. / Hagios Consulting Engineers
Contractor: Sitbec Ltd.

Proposed Contract Period: 80 weeks
Proposed Commencement Date: January 2, 2023
Proposed Completion Date: July 2, 2024
Time Elapsed: 55 weeks
Elapsed Time Percentage: 68.75%
Overall Progress Percentage: 39.5%

Superstructure block work in progress, except for hostels and the library. Pictures of work in progress can be see below.

Administration Block

Superstructure blockwork continues

Multipurpose Hall

Superstructure blockwork and basement work continues

Classrooms (4No)

Superstructure blockwork continues

Pavillions (4 No)

Setting of superstructure pillars

Laboratory (2 No)

Superstructure wall blockwork continues

Library

Concrete slab casting continues

Staff Housing (3 No)

Superstructure wall blockwork continues

Hostels (6 No)

Concrete slab casting in progress

Headmaster and Teachers' Housing

Superstructure wall blockwork

Cafeteria

Superstructure blockwork in progress

Other Pictures

Eastern classroom section
Superstructure wall blockwork (teachers housing)
Staff houses
Eastern side hostels
Site view
Site middle section view

###
end update

Progress Report – December 5, 2025

Work progresses as our completion dates nears. […]

Read More

Progress Report – September 30, 2025

Work progresses as our completion dates nears. […]

Read More

Site Plan – October 08, 2025

Work progresses as our completion dates nears. […]

Read More

Progress Report – August 1, 2025

Work progresses as our completion dates nears. […]

Read More

Progress Report – June 20, 2025

Work moving along steadily as we work toward completion. […]

Read More

Progress Report – June 5, 2025

Work continues as we aim to finish by the end of Summer. […]

Read More

Progress Report – May 30, 2025

With the main buildings close to completion, efforts turn toward completing the rectory and playing fields. […]

Read More

Progress Report – May 23, 2025

Work continues as we progress toward our completion date. […]

Read More

Progress Report – May 9, 2025

Work will continue through the summer with a new completion date of August 31, 2025. […]

Read More

Progress Report – April 11, 2025

Progress continues as we work toward a completion date of April 30, 2025. […]

Read More

HELP US

REACH OUR GOAL!

Working to complete Our Lady of Namulenga High School