Updated July 16, 2024
Client: The Archdiocese of Blantyre
Consultant: Team Lift Inc. / Hagios Consulting Engineers
Contractor: Sitbec Ltd.
Proposed Contract Period: 80 weeks
Proposed Time Extension:Â 9 weeks
Proposed Commencement Date: January 2, 2023
Proposed Completion Date: July 2, 2024
Revised Completion Date: August 31, 2024
Time Elapsed: 79 weeks
Elapsed Time Percentage: 98.5%
Revised Elapsed Time Percentage: 88%
Overall Progress Percentage: 79%
JULY TARGETS:
– Finalizing fabrication and fixing of steel roof trusses and iron sheets
– Finalizing window and door frames fixing
– Superstructure wall finishes continues
– Earth works and other external works continue
Pictures of work in progress can be see below.
Administration Block

Multipurpose Hall

Classrooms (2No)

Pavillions (2 No)

Laboratory (1 No)

Library

Staff Housing

Hostels (2 No)

Headmaster and Teachers' Housing

Cafeteria

Other Works
Fabrication & fixing of trusses, door & window frames continues


Ablution Blocks & Clock tower
– superstructure activities in progress (ablution block)
– substructure activities in progress(clocktower)


External Works
– Septic tank trench
* cleaning
* foundation base and column setting and excavation
– Road network & Carparks
* soil cutting
* road formation, soil clarification, mixing, and compaction
* subbase layer gravel filling
* gravel hauling inprogress


Electrical and Plumbing First Phase Activities in Progress
Other Pictures





###
end update