Updated June 26, 2024
Client: The Archdiocese of Blantyre
Consultant: Team Lift Inc. / Hagios Consulting Engineers
Contractor: Sitbec Ltd.
Proposed Contract Period: 80 weeks
Proposed Time Extension:Â 9 weeks
Proposed Commencement Date: January 2, 2023
Proposed Completion Date: July 2, 2024
Revised Completion Date: August 31, 2024
Time Elapsed: 76 weeks
Elapsed Time Percentage: 95%
Revised Elapsed Time Percentage: 85%
Overall Progress Percentage: 79%
JUNE TARGETS:
– Fabrication and installation of steel roof trusses continues.
– Window and door frame fabrication and fixing continues.
– Main site road networks continues.
– Superstructure wall finishes continues.
Pictures of work in progress can be see below.
Administration Block
Multipurpose Hall
Classrooms (2No)
Pavillions (2 No)
Laboratory (1 No)
Library
Staff Housing
Hostels (2 No)
Headmaster and Teachers' Housing
Cafeteria
Other Works
Ablution Blocks & Clocktower
– superstructure blockwork in progress
Fabrication & fixing of trusses, door & window frames continues
External Works:
– Septic tank trench excavation
– Road network
* soil cutting
* road formation soil clarification, mixing and compaction
Electrical and Plumbing First Phase Activities in Progress
Site general cleaning continues
Other Pictures
###
end update