Updated May 17, 2024
Client: The Archdiocese of Blantyre
Consultant: Team Lift Inc. / Hagios Consulting Engineers
Contractor: Sitbec Ltd.
Proposed Contract Period: 80 weeks
Proposed Time Extension:Â 9 weeks
Proposed Commencement Date: January 2, 2023
Proposed Completion Date: July 2, 2024
Revised Completion Date: August 31, 2024
Time Elapsed: 71 weeks
Elapsed Time Percentage: 88.75%
Revised Elapsed Time Percentage: 79.77%
Overall Progress Percentage: 74.5%
MAY TARGETS:
– Fabrication and installation of steel roof trusses.
– Window and door frame fabrication and fixing.
– Main site road networks.
– Superstructure wall finishes.
Pictures of work in progress can be see below.
Administration Block

Multipurpose Hall

Classrooms (2No)

Pavillions (2 No)

Laboratory (1 No)

Library

Staff Housing

Hostels (2 No)

Headmaster and Teachers' Housing

Cafeteria

Other Works
Ablution Blocks & Clocktower
– finalizing excavation and ready for footing

External works: road network
– Soil sample results are ready.
– Design levels
– Road soil cutting to start today
Electrical and plumbing first phase activities in progress
Site general cleaning continues
Fixing of trusses and door frames.


Other Pictures





###
end update