Updated May 13, 2024
Client: The Archdiocese of Blantyre
Consultant: Team Lift Inc. / Hagios Consulting Engineers
Contractor: Sitbec Ltd.
Proposed Contract Period: 80 weeks
Proposed Time Extension:Â 9 weeks
Proposed Commencement Date: January 2, 2023
Proposed Completion Date: July 2, 2024
Revised Completion Date: August 31, 2024
Time Elapsed: 69 weeks
Elapsed Time Percentage: 86.25%
Revised Elapsed Time Percentage: 77.52%
Overall Progress Percentage: 73.5%
MAY TARGETS:
Fabrication and installation of steel roof trusses.
Window and door frame fabrication and fixing.
Main site road networks.
Plastering finishes.
Pictures of work in progress can be see below.
Administration Block
Multipurpose Hall
Classrooms (2No)
Pavillions (2 No)
Laboratory (1 No)
Library
Staff Housing
Hostels (2 No)
Headmaster and Teachers' Housing
Cafeteria
Other Works
Ablution Blocks & Clocktower
– foundation excavation in progress
External works: road network
– testing soil samples both existing and borrow pits; clearing.
Electrical and plumbing first phase activities in progress
Site general cleaning continues
Fabrication and assembling of trusses continues
Administration and classes complete.
Other Pictures
###
end update