Updated June 3, 2024

Client: The Archdiocese of Blantyre
Consultant: Team Lift Inc. / Hagios Consulting Engineers
Contractor: Sitbec Ltd.

Proposed Contract Period: 80 weeks
Proposed Time Extension:  9 weeks
Proposed Commencement Date: January 2, 2023
Proposed Completion Date: July 2, 2024
Revised Completion Date: August 31, 2024
Time Elapsed: 73 weeks
Elapsed Time Percentage: 91%
Revised Elapsed Time Percentage: 82%
Overall Progress Percentage: 76.5%

JUNE TARGETS:

– Fabrication and installation of steel roof trusses continues.
– Window and door frame fabrication and fixing continues.
– Main site road networks continues.
– Superstructure wall finishes continues.

Pictures of work in progress can be see below.

Administration Block

Substructure wall finishes: Inside walls plastering continues; Door frames fixing in progress.

Multipurpose Hall

Blockwork in progress

Classrooms (2No)

Truss alignment and wall finishes continues; beam filling.

Pavillions (2 No)

Trusses and wall finishes in progress.

Laboratory (1 No)

Trusses and finishes; Inside room tables blockwork and slabs.

Library

Roof beam activities and wall finishes. Roof beam concrete casting continues; Inside wall plastering.

Staff Housing

Trusses and wall finishes. Wall plastering continues.

Hostels (2 No)

Trusses and wall finish preparations.

Headmaster and Teachers' Housing

Trusses and wall finish continues.

Cafeteria

Trusses and wall finish continues.

Other Works

Ablution Blocks & Clocktower
– foundation blockwork continues

foundation blockwork

Fixing of trusses and door frames

Trusses
Door frames

External Works: Road network
Road soil cutting

road soil cutting

Electrical and plumbing first phase activities in progress

Site general cleaning continues

Other Pictures

Site visit
Site visit
Steel truss connection
Fabrication of trusses for staff houses
Road works
Plumbing fittings fixing
Plastering inside teacher's house

###
end update

Progress Report – December 5, 2025

Work progresses as our completion dates nears. […]

Read More

Progress Report – September 30, 2025

Work progresses as our completion dates nears. […]

Read More

Site Plan – October 08, 2025

Work progresses as our completion dates nears. […]

Read More

Progress Report – August 1, 2025

Work progresses as our completion dates nears. […]

Read More

Progress Report – June 20, 2025

Work moving along steadily as we work toward completion. […]

Read More

Progress Report – June 5, 2025

Work continues as we aim to finish by the end of Summer. […]

Read More

Progress Report – May 30, 2025

With the main buildings close to completion, efforts turn toward completing the rectory and playing fields. […]

Read More

Progress Report – May 23, 2025

Work continues as we progress toward our completion date. […]

Read More

Progress Report – May 9, 2025

Work will continue through the summer with a new completion date of August 31, 2025. […]

Read More

Progress Report – April 11, 2025

Progress continues as we work toward a completion date of April 30, 2025. […]

Read More

HELP US

REACH OUR GOAL!

Working to complete Our Lady of Namulenga High School