Updated June 3, 2024

Client: The Archdiocese of Blantyre
Consultant: Team Lift Inc. / Hagios Consulting Engineers
Contractor: Sitbec Ltd.

Proposed Contract Period: 80 weeks
Proposed Time Extension:  9 weeks
Proposed Commencement Date: January 2, 2023
Proposed Completion Date: July 2, 2024
Revised Completion Date: August 31, 2024
Time Elapsed: 73 weeks
Elapsed Time Percentage: 91%
Revised Elapsed Time Percentage: 82%
Overall Progress Percentage: 76.5%

JUNE TARGETS:

– Fabrication and installation of steel roof trusses continues.
– Window and door frame fabrication and fixing continues.
– Main site road networks continues.
– Superstructure wall finishes continues.

Pictures of work in progress can be see below.

Administration Block

Substructure wall finishes: Inside walls plastering continues; Door frames fixing in progress.

Multipurpose Hall

Blockwork in progress

Classrooms (2No)

Truss alignment and wall finishes continues; beam filling.

Pavillions (2 No)

Trusses and wall finishes in progress.

Laboratory (1 No)

Trusses and finishes; Inside room tables blockwork and slabs.

Library

Roof beam activities and wall finishes. Roof beam concrete casting continues; Inside wall plastering.

Staff Housing

Trusses and wall finishes. Wall plastering continues.

Hostels (2 No)

Trusses and wall finish preparations.

Headmaster and Teachers' Housing

Trusses and wall finish continues.

Cafeteria

Trusses and wall finish continues.

Other Works

Ablution Blocks & Clocktower
– foundation blockwork continues

foundation blockwork

Fixing of trusses and door frames

Trusses
Door frames

External Works: Road network
Road soil cutting

road soil cutting

Electrical and plumbing first phase activities in progress

Site general cleaning continues

Other Pictures

Site visit
Site visit
Steel truss connection
Fabrication of trusses for staff houses
Road works
Plumbing fittings fixing
Plastering inside teacher's house

###
end update

Progress Report – September 12, 2024

New completion date has been set; work continues. […]

Read More

Progress Report – August 23, 2024

Work continues on track. […]

Read More

Progress Report – August 16, 2024

Progress continues. […]

Read More

Progress Report – July 26, 2024

New targets set for August. […]

Read More

Progress Report – July 12, 2024

Work continues on track. […]

Read More

Progress Report – June 21, 2024

Overall progress on project is at 79%. […]

Read More

Progress Report – June 14, 2024

Progress continues on June targets. […]

Read More

Progress Report – May 17, 2024

Overall completion percentage at 74.5%. […]

Read More

Progress Report – May 3, 2024

May targets on track; work continues. […]

Read More

Progress Report – April 19, 2024

April targets on track; work continues. […]

Read More

HELP US

REACH OUR GOAL!

Working to complete Our Lady of Namulenga High School