Updated November 26, 2024
Client: The Archdiocese of Blantyre
Consultant: Team Lift Inc. / Hagios Consulting Engineers
Contractor: Sitbec Ltd.
Proposed Contract Period: 80 weeks
Proposed Time Extension: 26 weeks
Proposed Commencement Date: January 2, 2023
Proposed Completion Date: July 2, 2024
Revised Completion Date: December 31, 2024
Time Elapsed: 97 weeks
Revised Elapsed Time Percentage: 91.5%
Overall Progress Percentage: 84.5%
NOVEMBER TARGETS:
ONGOING INSTALLATION OF TRUSSES AND IRON SHEETS FOR THE 1 REMAINING TEACHERS HOUSE, 3 PAVILIONS, 1 WESTERN CLASSBLOCK & LABORATORY, LIBRARY, CLOCKTOWER & 4 HOSTELS.
CONCLUDING SUPERSTRUCTURE BLOCKWORK FOR THE 4 REMAINING HOSTELS, 1 SEPTIC TANK & 4 ABLUTION BLOCKS (All up to roof level)
CEILING BLUNDERING FOR ADMNISTRATION, STAFF & TEACHERS HOUSES CONTINUES
ONGOING SUPERSTRUCTURE WALL FINISHES FOR ALL STRUCTURES
INTRODUCTION OF OTHER EXTERNAL WORKS (drainage systems)
ELECTRICAL AND PLUMBING WORKS FOR ALL STRUCTURES CONTINUES
Pictures of work in progress can be see below.
1.1 HOSTELS (6No)
1.2 Class Blocks (4No)
1.3 PAVILION (4NO)
1.4 LABORATORY (2NO)
LIBRARY
ABLUTION BLOCK 4NO
CLOCKTOWER 1NO & ADMINISTRATION
MULTIPURPOSE HALL, TEACHERS, & HEAD MASTERS HOUSE
CAFETERIA & STAFF HOUSES
Other Works
External Works
– Septic tank
Tank 1
* Ongoing top cover concrete casting activities
Tank 2
* Finalizing superstructure blockwork
Sewer drainage system 30%
* Setting out, excavation, cleaning, sand level checking, pipe fixing & sand & soil back filling
– Earth works 95%
* crusher run final finish pending
-Site road temporary drains 30%
Electrical and plumbing first phase activities in progress
Other Pictures
###
end update