Updated October 16, 2024
Client: The Archdiocese of Blantyre
Consultant: Team Lift Inc. / Hagios Consulting Engineers
Contractor: Sitbec Ltd.
Proposed Contract Period: 80 weeks
Proposed Time Extension: 26 weeks
Proposed Commencement Date: January 2, 2023
Proposed Completion Date: July 2, 2024
Revised Completion Date: December 31, 2024
Time Elapsed: 91 weeks
Revised Elapsed Time Percentage: 85.6%
Overall Progress Percentage: 79.5%
OCTOBER TARGETS:
CONTINUATION OF FIXING OF TRUSSES AND IRON SHEETS FOR THE 1 REMAINING TEACHERS HOUSE, 4 PAVILIONS, 2 WESTERN CLASSBLOCKS & LABORATORY, LIBRARY, CLOCKTOWER AND 4
HOSTELS.
FINALIZING SUPERSTRUCTURE BLOCKWORK FOR THE 4 REMAINING HOSTELS,
2 WESTERN CLASSBLOCKS, 2 WESTERN PAVILIONS, 1 WESTERN LABORATORY, 1 SEPTIC TANK AND 4 ABLUTION
BLOCKS (All up to roof level)
SUPERSTRUCTURE WALL FINISHES CONTINUE
ELECTRICAL AND PLUMBING WORK IN PROGRESS
FINALIZING EARTH WORKS & INTRODUCING OTHER REMAINING EXTERNAL WORKS
Pictures of work in progress can be see below.
1.1 HOSTELS (6No)
12 Class Blocks (4No)
1.3 PAVILION (4NO)
1.4 LABORATORY (2NO)
LIBRARY
ABLUTION BLOCK 4NO
CLOCKTOWER 1NO & ADMINISTRATION
MULTIPURPOSE HALL, TEACHERS, & HEAD MASTERS HOUSE
CAFETERIA & STAFF HOUSES
Other Works
External Works
– Septic tank
Tank 1
* Wall plastering: complete
* Top cover slab formwork, rebars, and concrete: preparations
Tank 2
* Setting out: complete
* Foundation base, beam, and column rebar bending: 80%
* Fixing, alignments, and concrete casting: next task
– Earth works (in progress)
* soil cutting: complete
* road formation, soil clarification, mixing, and compaction: complete
* subbase layer gravel filling and compacting: 95%
* base layer gravel filling and compacting: 0%
Electrical and plumbing first phase activities continue
Other Pictures
###
end update