Updated October 28, 2024

Client: The Archdiocese of Blantyre
Consultant: Team Lift Inc. / Hagios Consulting Engineers
Contractor: Sitbec Ltd.

Proposed Contract Period: 80 weeks
Proposed Time Extension:  26 weeks
Proposed Commencement Date: January 2, 2023
Proposed Completion Date: July 2, 2024
Revised Completion Date: December 31, 2024
Time Elapsed: 93 weeks
Revised Elapsed Time Percentage: 87.7%
Overall Progress Percentage: 80.5%

OCTOBER TARGETS:

CONTINUATION OF FIXING OF TRUSSES AND IRON SHEETS FOR THE 1 REMAINING TEACHERS HOUSE, 4  PAVILIONS,  2  WESTERN  CLASSBLOCKS  &  LABORATORY,  LIBRARY,  CLOCKTOWER  AND  4
HOSTELS.

FINALIZING  SUPERSTRUCTURE  BLOCKWORK  FOR  THE  4  REMAINING  HOSTELS,
2  WESTERN  CLASSBLOCKS, 2 WESTERN PAVILIONS, 1 WESTERN LABORATORY, 1 SEPTIC TANK AND 4 ABLUTION
BLOCKS (All up to roof level)

SUPERSTRUCTURE WALL FINISHES CONTINUE

ELECTRICAL AND PLUMBING WORK IN PROGRESS

FINALIZING EARTH WORKS & INTRODUCING OTHER REMAINING EXTERNAL WORKS

Pictures of work in progress can be see below.

1.1 HOSTELS (6No)

Hostels 2,3,5 & 6; continuation of ring be asting activities & after beam blockwork. Hostels 1 & 4; outside room wall finishes continue.

1.2 Class Blocks (4No)

Western Section (2No): Superstructure after beam blockwork and beam filling in progress. Finalizing truss fixing and ready for iron sheets. Eastern section (2No): Foul water drainage system activities in progress.

1.3 PAVILION (4NO)

Western Pavilions: All are ready for trusses (all preparations in progress.) Eastern Pavilions: fixing of trusses, purlins, and iron sheets in progress.

1.4 LABORATORY (2NO)

Western laboratory: Fixing of trusses in progress. Eastern laboratory: Drainage system activities in progress.

LIBRARY

Roofing activities continue. Fixing of trusses and purlins in progress.

ABLUTION BLOCK 4NO

Superstructure activities in progress. Casting of columns in progress; inside room wall plastering in progress.

CLOCKTOWER 1NO & ADMINISTRATION

Clock tower: Ready for trusses (all preparations are in progress.) Administration: Inside wall finishes continue 90%; ceiling fixing preparations in progress.

MULTIPURPOSE HALL, TEACHERS, & HEAD MASTERS HOUSE

Outside room wall finishes continue. Outside room wall skirting plaster; window and beam reveal.

CAFETERIA & STAFF HOUSES

Inside & Outside wall finishes continue. Beam and window reveal; skirting plaster and pointing.

Other Works

External Works
– Septic tank
Tank 1

* Wall plastering: complete
* Top cover slab formwork, rebars, and concrete: preparations

Tank 2
* Setting out: complete
* Foundation base, beam, and column rebar bending: 80%
* Fixing, alignments, and concrete casting: next task

– Earth works (in progress)
* soil cutting: complete
* road formation, soil clarification, mixing, and compaction: complete
* subbase layer gravel filling and compacting: 95%
* base layer gravel filling and compacting: 0%

Soil cutting

Electrical and plumbing first phase activities continue

Other Pictures

site plan
middle section site plan
Multipurpose Hall
Hostel blockwork
Site plan
Staff house inside room lime patty finish
Library trusses
Earthworks
Earthworks
Western section of the site

###
end update

Progress Report – October 11, 2024

New targets set for month of October. […]

Read More

Progress Report – September 12, 2024

New completion date has been set; work continues. […]

Read More

Progress Report – August 23, 2024

Work continues on track. […]

Read More

Progress Report – August 16, 2024

Progress continues. […]

Read More

Progress Report – July 26, 2024

New targets set for August. […]

Read More

Progress Report – July 12, 2024

Work continues on track. […]

Read More

Progress Report – June 21, 2024

Overall progress on project is at 79%. […]

Read More

Progress Report – June 14, 2024

Progress continues on June targets. […]

Read More

Progress Report – May 31, 2024

Progress continues with new June targets established. […]

Read More

Progress Report – May 17, 2024

Overall completion percentage at 74.5%. […]

Read More

HELP US

REACH OUR GOAL!

Working to complete Our Lady of Namulenga High School