Updated September 16, 2024
Client: The Archdiocese of Blantyre
Consultant: Team Lift Inc. / Hagios Consulting Engineers
Contractor: Sitbec Ltd.
Proposed Contract Period: 80 weeks
Proposed Time Extension: 26 weeks
Proposed Commencement Date: January 2, 2023
Proposed Completion Date: July 2, 2024
Revised Completion Date: December 31, 2024
Time Elapsed: 87 weeks
Revised Elapsed Time Percentage: 82%
Overall Progress Percentage: 74%
SUMMARY:
The construction focus has shifted back to structures that were left behind as per the initial school opening program.
Fixing of trusses and iron sheets for the two remaining teachers houses
– Two Eastern pavilions
– Two Western classblocks
– Library
– Two hostels
still in progress
Blockwork for the four remaining hostels
– Two Western classblocks
– Two Western pavilions
– One Western laboratory
– One septic tank
– Three ablution blocks
Clocktower
are targeted for completion as well
Pictures of work in progress can be see below.
2No Western & 2No Eastern hostels

Classroom blocks 2 East, 2 West

PAVILIONS 2No East: 2No West


LABORATORY East 1No West 1No

Library

Ablution Blocks 4No


Clocktower 1No & Administration

Multipurpose Hall

Cafeteria & Staff Houses


Other Works
External Works
– Septic tank
* Wall plastering (1st tank)
* Trench cleaning continues (2nd tank)
– Road network & Carparks
* soil cutting
* road formation, soil clarification, mixing, and compaction
* subbase layer gravel filling
* gravel hauling in progress
Electrical and plumbing first phase activities in progress
Other Pictures



###
end update