Updated August 12, 2026
Client: The Archdiocese of Blantyre
Consultant: Team Lift Inc. / Hagios Consulting Engineers
Contractor: Sitbec Ltd.
Class Blocks


Storm-Water Drainage and Roads
- Drain lining and covers, stone pitching & pointing in front of administration done
- Access lamps to Teaching Area completed
- Drain lining halfway around library done
- Water tap installation done
Pavilion

Eastern & Western Pavilion Classes
- Installation of doors on western classes done
Laboratory

Western and Eastern Laboratory
- Installation of water taps at pit latrines, hall, administration and teaching area completed
- Finalizing fascia boards installation done
Administration & Clocktower

- Construction of front storm water drain with covers done
- Clearing excavation spoil and boulders completed
- Completed and operational & ESCOM Electricity connection completed
- Water tap installation done
- Road and car park upgrading completed
Multipurpose

- The hall is completed and operational and ESCOM Electricity connection is completed
- Installation of underground cables for ESCOM electricity complete
- Water tap installation done
Hostels


- Black bituminous paint and brick sealer completed
- Surrounding landscaping 100% done
- All construction, electrical, and plumbing fittings are complete and operational
Library


- All construction and fitting are complete and operational
- Installation of underground cables and connection of ESCOM electricity completed
Teachers & Headmaster House

- All construction, facilities and fittings complete and operational.
- ESCOM electricity connection completed.
- Preparation for installation of drying lines in progress.
Sisters' Convent


- All construction and fittings are completed pending ESCOM electricity connection to the grid
Cafeteria Hall


- All construction and fittings are complete and operational pending installation of electric pots and its drainage system.
Football Pitch

New Eastern Septic Tank System


- Top slab casting 100% done
- Soak-pit Block-work completed pending top slab casting
- French drains excavation done and rock fill in progress
- Construction of manholes in progress-90%
- Manhole covers preparation in progress
###
end update









