Updated August 12, 2026

Client: The Archdiocese of Blantyre
Consultant: Team Lift Inc. / Hagios Consulting Engineers
Contractor: Sitbec Ltd.

Class Blocks

Storm water drain entrance to library section

Storm-Water Drainage and Roads

  • Drain lining and covers, stone pitching & pointing in front of administration done
  • Access lamps to Teaching Area completed
  • Drain lining halfway around library done
  • Water tap installation done

Pavilion

Western & Eastern Teaching area section

Eastern & Western Pavilion Classes

  • Installation of doors on western classes done

Laboratory

Eastern laboratory section

Western and Eastern Laboratory

  • Installation of water taps at pit latrines, hall, administration and teaching area completed
  • Finalizing fascia boards installation done

Administration & Clocktower

Aerial view of Administration
  • Construction of front storm water drain with covers done
  • Clearing excavation spoil and boulders completed
  • Completed and operational & ESCOM Electricity connection completed
  • Water tap installation done
  • Road and car park upgrading completed

Multipurpose

Aerial view of multipurpose hall
  • The hall is completed and operational and ESCOM Electricity connection is completed
  • Installation of underground cables for ESCOM electricity complete
  • Water tap installation done

Hostels

  • Black bituminous paint and brick sealer completed
  • Surrounding landscaping 100% done
  • All construction, electrical, and plumbing fittings are complete and operational

Library

Library aerial and interior views
  • All construction and fitting are complete and operational
  • Installation of underground cables and connection of ESCOM electricity completed

Teachers & Headmaster House

Aerial view of teacher houses
  • All construction, facilities and fittings complete and operational.
  • ESCOM electricity connection completed.
  • Preparation for installation of drying lines in progress.

Sisters' Convent

  • All construction and fittings are completed pending ESCOM electricity connection to the grid

Cafeteria Hall

Aerial and ground interior photos of cafeteria
  • All construction and fittings are complete and operational pending installation of electric pots and its drainage system.

Football Pitch

New Eastern Septic Tank System

Ground view of the new septic tank and the pipeline
  • Top slab casting 100% done
  • Soak-pit Block-work completed pending top slab casting
  • French drains excavation done and rock fill in progress
  • Construction of manholes in progress-90%
  • Manhole covers preparation in progress

###
end update

Progress Report – July 3, 2026

Finishing up extras around campus. […]

Read More

Progress Report – June 5, 2026

Finishing up extras around campus. […]

Read More

Progress Report – April 24, 2026

Work progresses as our completion dates nears. […]

Read More

Meet Our Student Communications Team

As part of sharing the journey and stories of Our Lady of Namlenga High School, six students have been chosen to help write and communicate about life at the school. With their help, people from all over the world can get to know the students, teachers, and faculty that make up Our Lady of Namlenga. […]

Read More

Progress Report – December 5, 2025

Work progresses as our completion dates nears. […]

Read More

Progress Report – September 30, 2025

Work progresses as our completion dates nears. […]

Read More

Site Plan – October 08, 2025

Work progresses as our completion dates nears. […]

Read More

Progress Report – August 1, 2025

Work progresses as our completion dates nears. […]

Read More

Progress Report – June 20, 2025

Work moving along steadily as we work toward completion. […]

Read More

Progress Report – June 5, 2025

Work continues as we aim to finish by the end of Summer. […]

Read More