Updated August 25, 2026
Client: The Archdiocese of Blantyre
Consultant: Team Lift Inc. / Hagios Consulting Engineers
Contractor: Sitbec Ltd.
Class Blocks


Storm-Water Drainage and Roads
- Drain lining and covers, stone pitching & pointing in front of administration done
- Access lamps to Teaching Area completed
- Drain lining halfway around library done
- Grading campus access roads done
Pavilion

Eastern & Western Pavilion Classes
- Installation of doors on western classes done
Laboratory

Western and Eastern Laboratory
- Installation of water taps at pit latrines, hall, administration and teaching area completed
- Finalizing fascia boards installation done
Administration & Clocktower

- Construction of front storm water drain with covers done
- Clearing excavation spoil and boulders completed
- Completed and operational & ESCOM Electricity connection completed
- Water tap installation done
- Road and car park upgrading completed
Multipurpose

- The hall is completed and operational and ESCOM Electricity connection is completed
- Installation of underground cables for ESCOM electricity complete
- Water tap installation done
Hostels


- Black bituminous paint and brick sealer completed
- Surrounding landscaping 100% done
- All construction, electrical, and plumbing fittings are complete and operational

- Black bituminous paint and brick sealer in progress
- Surrounding landscaping in progress
- Access road grading done
Library


- All construction and fitting are complete and operational
- Installation of underground cables and connection of ESCOM electricity completed
Teachers & Headmaster House

- All construction, facilities and fittings complete and operational.
- ESCOM electricity connection completed.
- Preparation for installation of drying lines in progress.
Sisters' Convent


- Ceiling board installation and painting done
- Electrical and plumbing fitting in progress
- Window glazing
- Floor tiles 95% done, grouting in progress
- Water tank stand done
- Splash pads/paving done
- Rain water gutter done
- First coat of interior paints
- Landcaping in progress: 90%


Father's Rectory


- Roofing done
- Internal primer coat of paint in progress
- External paint in progress- first coat done
- Ceiling to extended rooms done
- Ceiling painting in progress
Apartment Building



- All construction and fittings are complete, pending ESCOM electricity connection to grid
Cafeteria


- All construction and fittings are complete and operational pending installation of electric pots and its drainage system.
Football Pitch



- Watering, weeding and replanting grass in progress
- Ground Socket and Goal Posts fabrication and welding done
Staff Houses

- All construction and fittings are complete and operational pending road regarding and drain construction
Western & Eastern Ablution Blocks

- All Ablutions are complete and operational with lights connected
New Eastern Septic Tank System

- Top slab casting 100% done
- Soak-pit Block-work completed and slab casted
- French drains excavation done and rock fill done
- Construction of manholes in progress-90%
- Manhole covers done
Other Photos







Other Photos





###
end update