Updated August 25, 2026

Client: The Archdiocese of Blantyre
Consultant: Team Lift Inc. / Hagios Consulting Engineers
Contractor: Sitbec Ltd.

Class Blocks

Storm water drain; entrance to library

Storm-Water Drainage and Roads

  • Drain lining and covers, stone pitching & pointing in front of administration done
  • Access lamps to Teaching Area completed
  • Drain lining halfway around library done
  • Grading campus access roads done

Pavilion

Western & Eastern teaching area section

Eastern & Western Pavilion Classes

  • Installation of doors on western classes done

Laboratory

Eastern laboratory section

Western and Eastern Laboratory

  • Installation of water taps at pit latrines, hall, administration and teaching area completed
  • Finalizing fascia boards installation done

Administration & Clocktower

Aerial view of Administration building
  • Construction of front storm water drain with covers done
  • Clearing excavation spoil and boulders completed
  • Completed and operational & ESCOM Electricity connection completed
  • Water tap installation done
  • Road and car park upgrading completed

Multipurpose

Ground view of multipurpose building
  • The hall is completed and operational and ESCOM Electricity connection is completed
  • Installation of underground cables for ESCOM electricity complete
  • Water tap installation done

Hostels

Aerial view of western hostels
  • Black bituminous paint and brick sealer completed
  • Surrounding landscaping 100% done
  • All construction, electrical, and plumbing fittings are complete and operational
Aerial view Eastern hostel
  • Black bituminous paint and brick sealer in progress
  • Surrounding landscaping in progress
  • Access road grading done

Library

Interior of library
  • All construction and fitting are complete and operational
  • Installation of underground cables and connection of ESCOM electricity completed

Teachers & Headmaster House

Aerial view of teachers' houses
  • All construction, facilities and fittings complete and operational.
  • ESCOM electricity connection completed.
  • Preparation for installation of drying lines in progress.

Sisters' Convent

  • Ceiling board installation and painting done
  • Electrical and plumbing fitting in progress
  • Window glazing
  • Floor tiles 95% done, grouting in progress
  • Water tank stand done
  • Splash pads/paving done
  • Rain water gutter done
  • First coat of interior paints
  • Landcaping in progress: 90%

Father's Rectory

Ground photos of Rectory Building
  • Roofing done
  • Internal primer coat of paint in progress
  • External paint in progress- first coat done
  • Ceiling to extended rooms done
  • Ceiling painting in progress

Apartment Building

Aerial and ground views of apartment building
  • All construction and fittings are complete, pending ESCOM electricity connection to grid

Cafeteria

Aerial and interior view of cafeteria
  • All construction and fittings are complete and operational pending installation of electric pots and its drainage system.

Football Pitch

Ground view of pitch, goal posts, and ground sockets
  • Watering, weeding and replanting grass in progress
  • Ground Socket and Goal Posts fabrication and welding done

Staff Houses

Aerial view of staff houses
  • All construction and fittings are complete and operational pending road regarding and drain construction

Western & Eastern Ablution Blocks

Aerial view of Eastern ablution block
  • All Ablutions are complete and operational with lights connected

New Eastern Septic Tank System

Ground view of new septic tank and the pipeline
  • Top slab casting 100% done
  • Soak-pit Block-work completed and slab casted
  • French drains excavation done and rock fill done
  • Construction of manholes in progress-90%
  • Manhole covers done

Other Photos

Other Photos

###
end update

Progress Report – August 7, 2026

Finishing up extras around campus. […]

Read More

Progress Report – July 3, 2026

Finishing up extras around campus. […]

Read More

Progress Report – June 5, 2026

Finishing up extras around campus. […]

Read More

Progress Report – April 24, 2026

Work progresses as our completion dates nears. […]

Read More

Meet Our Student Communications Team

As part of sharing the journey and stories of Our Lady of Namlenga High School, six students have been chosen to help write and communicate about life at the school. With their help, people from all over the world can get to know the students, teachers, and faculty that make up Our Lady of Namlenga. […]

Read More

Progress Report – December 5, 2025

Work progresses as our completion dates nears. […]

Read More

Progress Report – September 30, 2025

Work progresses as our completion dates nears. […]

Read More

Site Plan – October 08, 2025

Work progresses as our completion dates nears. […]

Read More

Progress Report – August 1, 2025

Work progresses as our completion dates nears. […]

Read More

Progress Report – June 20, 2025

Work moving along steadily as we work toward completion. […]

Read More

HELP US

REACH OUR GOAL!

Working to complete Our Lady of Namulenga High School