Updated July 7, 2026

Client: The Archdiocese of Blantyre
Consultant: Team Lift Inc. / Hagios Consulting Engineers
Contractor: Sitbec Ltd.

Class Blocks

Storm water drain Administration - Staff houses section

Western & Eastern Storm-Water Drainage

  • Drain lining and covers, stone pitching & pointing in front of administration done
  • Access lamps to Teaching Area completed
  • Drain lining halfway around library done
  • Water tap installation done

Pavilion

Western and Eastern Teaching area section

Eastern & Western Pavilion Classes

  • External doors preparation done, installation on western classes in progress.

Laboratory

Western laboratory section

Western and Eastern Laboratory

  • Installation of water taps at pit latrines, hall, administration and teaching area completed
  • Finalizing Fascia boards installation to resume soon

Administration & Clocktower

Aerial view of Administration
  • Construction of front storm water drain with covers done
  • Clearing excavation spoil and boulders completed
  • Completed and operational & ESCOM Electricity connection completed
  • Water tap installation done

Multipurpose

Aerial view of multipurpose hall
  • The hall is completed and operational and ESCOM Electricity connection is completed
  • Installation of underground cables for ESCOM electricity complete
  • Water tap installation done
Ground view of transformer fence

Hostels

Ground view of hostel no. 25
  • Girls Hostel 1 is complete and operational.
  • Installation of underground cables and connection to ESCOM electricity complete
Aerial view of western hostels
  • Painting final touches, external bituminous and brick sealer preparations in progress
  • Surrounding landscaping 90% progress

Eastern Hostel No. 28

Ground view of Eastern hostel no. 2
  • The hostel is complete and operational
  • Installation of underground cables and ESCOM electricity connection complete
  • Main Water Tank pump connection to ESCOM electricity done

Eastern Hostels (all)

Eastern hostels aerial view
  • Internal Paint touch ups in progress
  • Preparation for external black bituminous and brick sealer application in progress
  • Surrounding landscaping in progress

Library

Aerial view and interior of library
  • All construction and fitting are complete and operational
  • Installation of underground cables and connection of ESCOM electricity completed

Teachers & Headmaster House

Aerial view of teachers' houses
  • All construction, facilities and fittings complete and operational.
  • ESCOM electricity connection completed.
  • Preparation for installation of drying lines in progress.

Sisters' Convent

Aerial view sisters' convent
  • Internal and external plaster completed
  • Roofing completed
  • Preparation for blandering in progress
  • Septic tank block work and casting in progress
  • Soak-pit block work completed
  • After wall plate block work completed
  • Window sills and air-vents installation done

Father's Rectory

Aerial view of rectory building
  • Roofing in progress

Apartment Building

  • All construction and fittings are completed pending ESCOM electricity connection to the grid

Cafeteria Hall

Aerial view of cafeteria
Interior photo of cafeteria
  • All construction and fittings are complete and operational pending installation of electric pots and its drainage system.

Football Pitch

Ground view of pitch
Goal posts awaiting installation
Ground sockets
  • Watering, weeding and replanting grass in progress
  • Ground Socket and Goal Posts fabrication 90% complete pending installation.

Staff Houses

Aerial view of staff houses
  • All construction and fittings are complete and operational pending road regarding and drain construction

Western & Eastern Ablution Blocks

Aerial view of eastern ablution
  • All ablutions are completed and operational with lights connected

New Eastern Septic Tank System

Ground view of new septic tank

New Eastern Septic Tank System

  • Decking formwork 70% progress pending top slab casting.
  • Soak-pit Block-work 85% in progress pending top slab casting.
  • Excavation for pipeline laying from hostel to tank completed
  • Levelling in progress pending Rerouting pipeline and reconstruction of manholes.
  • Preparation for French drains excavation in progress

Other Photos

###
end update

Progress Report – June 5, 2026

Finishing up extras around campus. […]

Read More

Progress Report – April 24, 2026

Work progresses as our completion dates nears. […]

Read More

Meet Our Student Communications Team

As part of sharing the journey and stories of Our Lady of Namlenga High School, six students have been chosen to help write and communicate about life at the school. With their help, people from all over the world can get to know the students, teachers, and faculty that make up Our Lady of Namlenga. […]

Read More

Progress Report – December 5, 2025

Work progresses as our completion dates nears. […]

Read More

Progress Report – September 30, 2025

Work progresses as our completion dates nears. […]

Read More

Site Plan – October 08, 2025

Work progresses as our completion dates nears. […]

Read More

Progress Report – August 1, 2025

Work progresses as our completion dates nears. […]

Read More

Progress Report – June 20, 2025

Work moving along steadily as we work toward completion. […]

Read More

Progress Report – June 5, 2025

Work continues as we aim to finish by the end of Summer. […]

Read More

Progress Report – May 30, 2025

With the main buildings close to completion, efforts turn toward completing the rectory and playing fields. […]

Read More