Updated July 7, 2026
Client: The Archdiocese of Blantyre
Consultant: Team Lift Inc. / Hagios Consulting Engineers
Contractor: Sitbec Ltd.
Class Blocks


Western & Eastern Storm-Water Drainage
- Drain lining and covers, stone pitching & pointing in front of administration done
- Access lamps to Teaching Area completed
- Drain lining halfway around library done
- Water tap installation done
Pavilion

Eastern & Western Pavilion Classes
- External doors preparation done, installation on western classes in progress.
Laboratory

Western and Eastern Laboratory
- Installation of water taps at pit latrines, hall, administration and teaching area completed
- Finalizing Fascia boards installation to resume soon
Administration & Clocktower

- Construction of front storm water drain with covers done
- Clearing excavation spoil and boulders completed
- Completed and operational & ESCOM Electricity connection completed
- Water tap installation done
Multipurpose

- The hall is completed and operational and ESCOM Electricity connection is completed
- Installation of underground cables for ESCOM electricity complete
- Water tap installation done

Hostels

- Girls Hostel 1 is complete and operational.
- Installation of underground cables and connection to ESCOM electricity complete

- Painting final touches, external bituminous and brick sealer preparations in progress
- Surrounding landscaping 90% progress
Eastern Hostel No. 28

- The hostel is complete and operational
- Installation of underground cables and ESCOM electricity connection complete
- Main Water Tank pump connection to ESCOM electricity done
Eastern Hostels (all)

- Internal Paint touch ups in progress
- Preparation for external black bituminous and brick sealer application in progress
- Surrounding landscaping in progress
Library


- All construction and fitting are complete and operational
- Installation of underground cables and connection of ESCOM electricity completed
Teachers & Headmaster House

- All construction, facilities and fittings complete and operational.
- ESCOM electricity connection completed.
- Preparation for installation of drying lines in progress.
Sisters' Convent




- Internal and external plaster completed
- Roofing completed
- Preparation for blandering in progress
- Septic tank block work and casting in progress
- Soak-pit block work completed
- After wall plate block work completed
- Window sills and air-vents installation done
Father's Rectory

- Roofing in progress
Apartment Building



- All construction and fittings are completed pending ESCOM electricity connection to the grid
Cafeteria Hall


- All construction and fittings are complete and operational pending installation of electric pots and its drainage system.
Football Pitch



- Watering, weeding and replanting grass in progress
- Ground Socket and Goal Posts fabrication 90% complete pending installation.
Staff Houses

- All construction and fittings are complete and operational pending road regarding and drain construction
Western & Eastern Ablution Blocks

- All ablutions are completed and operational with lights connected
New Eastern Septic Tank System

New Eastern Septic Tank System

- Decking formwork 70% progress pending top slab casting.
- Soak-pit Block-work 85% in progress pending top slab casting.
- Excavation for pipeline laying from hostel to tank completed
- Levelling in progress pending Rerouting pipeline and reconstruction of manholes.
- Preparation for French drains excavation in progress
Other Photos
















###
end update