Updated April 27, 2026

Client: The Archdiocese of Blantyre
Consultant: Team Lift Inc. / Hagios Consulting Engineers
Contractor: Sitbec Ltd.

Class Blocks

Storm water drain Entrance-Library section

Western & Eastern Sections

  • Storm-water drains masonry lining on the entrance to Library section completed, cleaning and clearing completed
  • Access lamps to teaching area 93% complete
  • Excavation and base footing halfway around library done

Pavilion

Western Pavilion Class Section

Laboratory

Western & Eastern Laboratory
  • Finalizing Fascia boards installation to resume soon

Administration & Clocktower

Aerial View of Administration
  • Paved walk ways connecting Eastern classes done
  • Installation of underground cables for ESCOM electricity from transformer point complete
  • Construction of transformer fence; plinth construction, steel fencing and painting 100%
  • Completed and ESCOM connection to the grid completed.

Multipurpose

Aerial view of Multipurpose Hall
  • The hall is completed and operational and ESCOM Electricity connection is completed
  • Installation of underground cables for ESCOM electricity complete
Ground view of transformer fence

Hostels

Aerial view of hostel no. 25
  • Girls Hostel 1 is complete and operational.
  • Installation of underground cables and connection to ESCOM electricity complete
Aerial and ground view of Western hostels
  • General cleaning and wall sanding completed pending painting
  • External door installation in progress
  • Plumbing final fittings and installations in progress
  • Electrical fittings all completed

Eastern Hostel No. 2

Ground view of Eastern Hostel No. 2
  • The hostel is complete and operational.
  • Installation of underground cables and ESCOM electricity connection complete
Eastern hostels aerial view
  • Glazing completed
  • Walls and window and door frame cleaning completed pending painting and door installation
  • Plumbing and Electrical fittings and connections (ESCOM Electricity and Water) completed

Library

Library aerial view
  • All construction and fitting are complete and operational
  • Installation of underground cables and connection of ESCOM electricity completed

Teachers & Headmaster House

Aerial view of teachers' houses
  • All construction, facilities and fittings complete and operational.
  • ESCOM electricity connection completed.

Sisters' Convent

Aerial view of sisters' convent building
  • Veranda column and beam casting 75% progress
  • Internal plaster in 90% progress
  • Internal window reveals 80% done
  • Timber Roofing (tie beams, kingposts and rafters installation) in progress
  • Supply electricity connection poles and cable lines done

Father's Rectory

Aerial view of rectory building
  • On hold pending beam filling and roofing

Apartment Building

Aerial and ground photos of apartment building
  • Internal and external doors installation, locks & painting completed
  • Landscaping around the building 98% completed
  • External and Internal painting completed
  • Electrical wiring and fittings completed pending connection to grid
  • Plumbing works and fittings completed
  • Septic tanks system reconditioning in progress
  • Fascia boards installation completed

Cafeteria Hall

Aerial and ground interior photos of Cafeteria

Football Pitch

Weeds clearing pending installation of goal posts

Staff Houses

Aerial view of staff houses
  • All construction and fittings are complete and operational
  • Preparations for Storm water drain construction in progress
  • Construction of outlet drain and drift to resume soon
  • ESCOM electricity connection completed.

Western & Eastern Ablution Blocks

New Eastern Septic Tank System

  • OGL and Invert levels for the pipe line and the tank taken
  • Setting out and staking for the line and tank done
  • Excavation of the septic tank 90% in progress
  • Preparation for reconstruction of manholes in progress

Other Photos

###
end update

Progress Report – July 3, 2026

Finishing up extras around campus. […]

Read More

Progress Report – June 5, 2026

Finishing up extras around campus. […]

Read More

Meet Our Student Communications Team

As part of sharing the journey and stories of Our Lady of Namlenga High School, six students have been chosen to help write and communicate about life at the school. With their help, people from all over the world can get to know the students, teachers, and faculty that make up Our Lady of Namlenga. […]

Read More

Progress Report – December 5, 2025

Work progresses as our completion dates nears. […]

Read More

Progress Report – September 30, 2025

Work progresses as our completion dates nears. […]

Read More

Site Plan – October 08, 2025

Work progresses as our completion dates nears. […]

Read More

Progress Report – August 1, 2025

Work progresses as our completion dates nears. […]

Read More

Progress Report – June 20, 2025

Work moving along steadily as we work toward completion. […]

Read More

Progress Report – June 5, 2025

Work continues as we aim to finish by the end of Summer. […]

Read More

Progress Report – May 30, 2025

With the main buildings close to completion, efforts turn toward completing the rectory and playing fields. […]

Read More

HELP US

REACH OUR GOAL!

Working to complete Our Lady of Namulenga High School