Updated April 27, 2026
Client: The Archdiocese of Blantyre
Consultant: Team Lift Inc. / Hagios Consulting Engineers
Contractor: Sitbec Ltd.
Class Blocks

Western & Eastern Sections
- Storm-water drains masonry lining on the entrance to Library section completed, cleaning and clearing completed
- Access lamps to teaching area 93% complete
- Excavation and base footing halfway around library done
Pavilion

Laboratory

- Finalizing Fascia boards installation to resume soon
Administration & Clocktower

- Paved walk ways connecting Eastern classes done
- Installation of underground cables for ESCOM electricity from transformer point complete
- Construction of transformer fence; plinth construction, steel fencing and painting 100%
- Completed and ESCOM connection to the grid completed.
Multipurpose

- The hall is completed and operational and ESCOM Electricity connection is completed
- Installation of underground cables for ESCOM electricity complete

Hostels

- Girls Hostel 1 is complete and operational.
- Installation of underground cables and connection to ESCOM electricity complete

- General cleaning and wall sanding completed pending painting
- External door installation in progress
- Plumbing final fittings and installations in progress
- Electrical fittings all completed
Eastern Hostel No. 2

- The hostel is complete and operational.
- Installation of underground cables and ESCOM electricity connection complete

- Glazing completed
- Walls and window and door frame cleaning completed pending painting and door installation
- Plumbing and Electrical fittings and connections (ESCOM Electricity and Water) completed
Library



- All construction and fitting are complete and operational
- Installation of underground cables and connection of ESCOM electricity completed
Teachers & Headmaster House

- All construction, facilities and fittings complete and operational.
- ESCOM electricity connection completed.
Sisters' Convent

- Veranda column and beam casting 75% progress
- Internal plaster in 90% progress
- Internal window reveals 80% done
- Timber Roofing (tie beams, kingposts and rafters installation) in progress
- Supply electricity connection poles and cable lines done
Father's Rectory

- On hold pending beam filling and roofing
Apartment Building



- Internal and external doors installation, locks & painting completed
- Landscaping around the building 98% completed
- External and Internal painting completed
- Electrical wiring and fittings completed pending connection to grid
- Plumbing works and fittings completed
- Septic tanks system reconditioning in progress
- Fascia boards installation completed
Cafeteria Hall


Football Pitch

Staff Houses

- All construction and fittings are complete and operational
- Preparations for Storm water drain construction in progress
- Construction of outlet drain and drift to resume soon
- ESCOM electricity connection completed.
Western & Eastern Ablution Blocks

New Eastern Septic Tank System

- OGL and Invert levels for the pipe line and the tank taken
- Setting out and staking for the line and tank done
- Excavation of the septic tank 90% in progress
- Preparation for reconstruction of manholes in progress
Other Photos










###
end update