Updated June 8, 2026
Client: The Archdiocese of Blantyre
Consultant: Team Lift Inc. / Hagios Consulting Engineers
Contractor: Sitbec Ltd.
Class Blocks

Western & Eastern Storm-Water Drainage
- Storm-water drains masonry lining on the entrance to Library section completed, cleaning and clearing sides spoil in progress
- Drain lining and covers in front of administration with done, cleaning in progress
- Access lamps to teaching area completed
- Drain lining halfway around library done
Pavilion

Eastern & Western Pavilion Classes
- External doors preparation done, installation on western classes in progress.
Laboratory

Western and Eastern Laboratory
- Preparations for installation of stand pipes taps in progress
- Finalizing Fascia boards installation to resume soon
Administration & Clocktower

- Construction of front storm water drain with covers done
- Clearing excavation spoil and boulders in progress
- Completed and operational and ESCOM Electricity connection completed
Multipurpose

- The hall is completed and operational and ESCOM Electricity connection is completed
- Installation of underground cables for ESCOM electricity complete

Hostels

- Girls Hostel 1 is complete and operational.
- Installation of underground cables and connection to ESCOM electricity complete

- Painting final coats complete, touch ups in progress in western hostels
- External door installation 100% complete
- Plumbing final fittings and installations completed
- Electricity and water connection all completed and operational
- Surrounding land-scaping in progress
Eastern Hostel No. 28

- The hostel is complete and operational.
- Installation of underground cables and ESCOM electricity connection complete
Eastern Hostels (all)

- Glazing completed
- Paint Primer and grey 1st coat done in hostel 30
- Door installation completed in all hostels
- Final plumbing fittings 98% in progress
- Electrical fittings and connections (ESCOM Electricity) completed
- Surrounding landscaping 97% in progress
Library


- All construction and fitting are complete and operational
- Installation of underground cables and connection of ESCOM electricity completed
Teachers & Headmaster House

- All construction, facilities and fittings complete and operational.
- ESCOM electricity connection completed.
Sisters' Convent

- Beam filling completed
- Timber Roof frame completed, iron sheets installation in progress
- Internal plaster in 96% progress
- Internal window reveals 100% done
- Supply electricity connection poles and cable lines done
- Septic tank block work and soak pit excavation in progress
Father's Rectory

- On hold pending pending plaster, beam filling, and roofing after electricity connection at the apartment
Apartment Building



- Electrical wiring and fittings completed pending connection to grid
- Septic tanks system reconditioning completed
- Water connection done
- Installation of wool-drobes, shelves and toilet/bath accessories 98% progress
- Surrounding landscaping completed
Cafeteria Hall


- All construction and fittings are complete and operational.
- Installation of underground cables and ESCOM electricity connection completed
- Preparation for installation of electric pots in progress
- Drain extension into storm water drain done.
Football Pitch

Staff Houses

- All construction and fittings are complete and operational
- Preparations for Storm water drain construction in progress
- Construction of outlet drain and drift to resume soon
- ESCOM electricity connection completed.
Western & Eastern Ablution Blocks

- All ablutions are completed and operational, pending lights connection
New Eastern Septic Tank System

- Excavation of the septic tank 100% done
- Column and base footing steel fixing completed, Column base footing casting done.
- Steel fixing and formwork for base slab completed, casting to commence tomorrow
- Preparation for reconstruction of manholes in progress
- Walls footing block-work completed
Other Photos










###
end update