Updated June 8, 2026

Client: The Archdiocese of Blantyre
Consultant: Team Lift Inc. / Hagios Consulting Engineers
Contractor: Sitbec Ltd.

Class Blocks

Storm water drain Administration-Staff Houses section

Western & Eastern Storm-Water Drainage

  • Storm-water drains masonry lining on the entrance to Library section completed, cleaning and clearing sides spoil in progress
  • Drain lining and covers in front of administration with done, cleaning in progress
  • Access lamps to teaching area completed
  • Drain lining halfway around library done

Pavilion

Western Pavilion class section

Eastern & Western Pavilion Classes

  • External doors preparation done, installation on western classes in progress.

Laboratory

Western Laboratory Section

Western and Eastern Laboratory

  • Preparations for installation of stand pipes taps in progress
  • Finalizing Fascia boards installation to resume soon

Administration & Clocktower

Ground view of administration
  • Construction of front storm water drain with covers done
  • Clearing excavation spoil and boulders in progress
  • Completed and operational and ESCOM Electricity connection completed

Multipurpose

Aerial view of multipurpose hall
  • The hall is completed and operational and ESCOM Electricity connection is completed
  • Installation of underground cables for ESCOM electricity complete
Ground view of transformer fence

Hostels

Ground view of hostel no. 25
  • Girls Hostel 1 is complete and operational.
  • Installation of underground cables and connection to ESCOM electricity complete
Aerial and ground view of western hostels
  • Painting final coats complete, touch ups in progress in western hostels
  • External door installation 100% complete
  • Plumbing final fittings and installations completed
  • Electricity and water connection all completed and operational
  • Surrounding land-scaping in progress

Eastern Hostel No. 28

ground view of Eastern hostel
  • The hostel is complete and operational.
  • Installation of underground cables and ESCOM electricity connection complete

Eastern Hostels (all)

Eastern hostels aerial view
  • Glazing completed
  • Paint Primer and grey 1st coat done in hostel 30
  • Door installation completed in all hostels
  • Final plumbing fittings 98% in progress
  • Electrical fittings and connections (ESCOM Electricity) completed
  • Surrounding landscaping 97% in progress

Library

Aerial view of library
Interior view of library
  • All construction and fitting are complete and operational
  • Installation of underground cables and connection of ESCOM electricity completed

Teachers & Headmaster House

Aerial view of teachers' houses
  • All construction, facilities and fittings complete and operational.
  • ESCOM electricity connection completed.

Sisters' Convent

Aerial view of sisters' convent building
  • Beam filling completed
  • Timber Roof frame completed, iron sheets installation in progress
  • Internal plaster in 96% progress
  • Internal window reveals 100% done
  • Supply electricity connection poles and cable lines done
  • Septic tank block work and soak pit excavation in progress

Father's Rectory

Aerial view of rectory building
  • On hold pending pending plaster, beam filling, and roofing after electricity connection at the apartment

Apartment Building

Aerial and ground photos of apartment building
  • Electrical wiring and fittings completed pending connection to grid
  • Septic tanks system reconditioning completed
  • Water connection done
  • Installation of wool-drobes, shelves and toilet/bath accessories 98% progress
  • Surrounding landscaping completed

Cafeteria Hall

Aerial view of cafeteria
Interior photo of cafeteria
  • All construction and fittings are complete and operational.
  • Installation of underground cables and ESCOM electricity connection completed
  • Preparation for installation of electric pots in progress
  • Drain extension into storm water drain done.

Football Pitch

Weeds clearing pending installation of goal posts

Staff Houses

Aerial view of staff houses
  • All construction and fittings are complete and operational
  • Preparations for Storm water drain construction in progress
  • Construction of outlet drain and drift to resume soon
  • ESCOM electricity connection completed.

Western & Eastern Ablution Blocks

Aerial view of Eastern ablution block
  • All ablutions are completed and operational, pending lights connection

New Eastern Septic Tank System

Aerial view of the new septic tank
  • Excavation of the septic tank 100% done
  • Column and base footing steel fixing completed, Column base footing casting done.
  • Steel fixing and formwork for base slab completed, casting to commence tomorrow
  • Preparation for reconstruction of manholes in progress
  • Walls footing block-work completed

Other Photos

Aerial view of campus

###
end update

Progress Report – July 3, 2026

Finishing up extras around campus. […]

Read More

Progress Report – April 24, 2026

Work progresses as our completion dates nears. […]

Read More

Meet Our Student Communications Team

As part of sharing the journey and stories of Our Lady of Namlenga High School, six students have been chosen to help write and communicate about life at the school. With their help, people from all over the world can get to know the students, teachers, and faculty that make up Our Lady of Namlenga. […]

Read More

Progress Report – December 5, 2025

Work progresses as our completion dates nears. […]

Read More

Progress Report – September 30, 2025

Work progresses as our completion dates nears. […]

Read More

Site Plan – October 08, 2025

Work progresses as our completion dates nears. […]

Read More

Progress Report – August 1, 2025

Work progresses as our completion dates nears. […]

Read More

Progress Report – June 20, 2025

Work moving along steadily as we work toward completion. […]

Read More

Progress Report – June 5, 2025

Work continues as we aim to finish by the end of Summer. […]

Read More

Progress Report – May 30, 2025

With the main buildings close to completion, efforts turn toward completing the rectory and playing fields. […]

Read More