Updated March 29, 2024

March Targets:

  • Completion of ring beam and block walls construction – to be done
  • Procurement, fabrication, and installation of steel roof trusses – in progress
  • Procurement of steel roof sheets, window and door frames, and setting out storm water and foul drainage structures – in progress

April Targets:

  • Fixing door and window frames
  • Assembling and fixing roof trusses
  • Plastering
  • Setting out of ablution blocks and clock tower

Pictures of ongoing construction work can be seen below.

Administration Block

Finalizing upper blockwork

Multipurpose Hall

Basement top slab formwork; rebar fixing in progress

Classrooms (2No)

After beam blockwork continues

Pavillions (2 No)

Finalizing column casting and ready for the concrete beam

Laboratory (1 No)

After ring beam blockwork

Library

Ready for ring beam and inside column casting continues

Staff Housing (3 No)

Ring beam casting continues; ready for after beam blockwork

Hostels (2 No)

Finalizing super structure blockwork; ready for ring beam

Headmaster and Teachers' Housing

Ring beam casting continues

Cafeteria

Ring beam form work and rebar fixing

Other Pictures

Critical section of classroom, laboratory, and pavilion
Classrooms, lab, and pavilions
All site construction
Library column
Pavilion column
Ring beam reinforcement

###
end update

Progress Report – December 5, 2025

Work progresses as our completion dates nears. […]

Read More

Progress Report – September 30, 2025

Work progresses as our completion dates nears. […]

Read More

Site Plan – October 08, 2025

Work progresses as our completion dates nears. […]

Read More

Progress Report – August 1, 2025

Work progresses as our completion dates nears. […]

Read More

Progress Report – June 20, 2025

Work moving along steadily as we work toward completion. […]

Read More

Progress Report – June 5, 2025

Work continues as we aim to finish by the end of Summer. […]

Read More

Progress Report – May 30, 2025

With the main buildings close to completion, efforts turn toward completing the rectory and playing fields. […]

Read More

Progress Report – May 23, 2025

Work continues as we progress toward our completion date. […]

Read More

Progress Report – May 9, 2025

Work will continue through the summer with a new completion date of August 31, 2025. […]

Read More

Progress Report – April 11, 2025

Progress continues as we work toward a completion date of April 30, 2025. […]

Read More

HELP US

REACH OUR GOAL!

Working to complete Our Lady of Namulenga High School