Updated March 29, 2024

March Targets:

  • Completion of ring beam and block walls construction – to be done
  • Procurement, fabrication, and installation of steel roof trusses – in progress
  • Procurement of steel roof sheets, window and door frames, and setting out storm water and foul drainage structures – in progress

April Targets:

  • Fixing door and window frames
  • Assembling and fixing roof trusses
  • Plastering
  • Setting out of ablution blocks and clock tower

Pictures of ongoing construction work can be seen below.

Administration Block

Finalizing upper blockwork

Multipurpose Hall

Basement top slab formwork; rebar fixing in progress

Classrooms (2No)

After beam blockwork continues

Pavillions (2 No)

Finalizing column casting and ready for the concrete beam

Laboratory (1 No)

After ring beam blockwork

Library

Ready for ring beam and inside column casting continues

Staff Housing (3 No)

Ring beam casting continues; ready for after beam blockwork

Hostels (2 No)

Finalizing super structure blockwork; ready for ring beam

Headmaster and Teachers' Housing

Ring beam casting continues

Cafeteria

Ring beam form work and rebar fixing

Other Pictures

Critical section of classroom, laboratory, and pavilion
Classrooms, lab, and pavilions
All site construction
Library column
Pavilion column
Ring beam reinforcement

###
end update

Progress Report – February 14, 2025

We are making excellent progress and have set a new tentative completion date of April 30, 2025. […]

Read More

Progress Report – January 17, 2025

Major milestones for the next fortnight have been set. Challenges such as material delivery delays and adverse weather conditions will require close monitoring. […]

Read More

Progress Report – December 06, 2024

Work progresses as we continue to reach toward milestones. […]

Read More

Progress Report – November 22, 2024

New targets set for November. […]

Read More

Progress Report – October 25, 2024

Work continues, moving toward targets. […]

Read More

Progress Report – October 11, 2024

New targets set for month of October. […]

Read More

Progress Report – September 12, 2024

New completion date has been set; work continues. […]

Read More

Progress Report – August 23, 2024

Work continues on track. […]

Read More

Progress Report – August 16, 2024

Progress continues. […]

Read More

Progress Report – July 26, 2024

New targets set for August. […]

Read More

HELP US

REACH OUR GOAL!

Working to complete Our Lady of Namulenga High School