Updated March 29, 2024
March Targets:
- Completion of ring beam and block walls construction – to be done
- Procurement, fabrication, and installation of steel roof trusses – in progress
- Procurement of steel roof sheets, window and door frames, and setting out storm water and foul drainage structures – in progress
April Targets:
- Fixing door and window frames
- Assembling and fixing roof trusses
- Plastering
- Setting out of ablution blocks and clock tower
Pictures of ongoing construction work can be seen below.