Updated September 25, 2023

Client: The Archdiocese of Blantyre (TTE/Diocese of Joliet)
Consultant: Team Lift Inc. / Hagios Consulting Engineers
Contractor: Sitbec Ltd.

Proposed Contract Period: 80 weeks
Proposed Commencement Date: January 2, 2023
Proposed Completion Date: July 2, 2024
Time Elapsed: 38 weeks

Pictures of ongoing construction work can be seen below.

Administration Block

Foundation block work completed. Soil back filling and compaction, ant treatment in progress in readiness for the reinforced concrete floor slab.

Multipurpose Hall

Foundation block work in progress

Classrooms (4No)

Foundation block work in progress.

Pavillions (4 No)

Foundation block work complete.

Laboratory (2 No)

Foundation block work complete.

Library

Foundation excavation is in progress. (Delayed structural details.)

Staff Housing (3 No)

Foundation concrete footing completed; foundation block work in progress.

Headmaster and Teachers' Housing

Foundation concrete footing completed. Foundation block work in progress.

Other Works

1. Lavatory
Excavation and cleaning: 100%
Footing: 100%
Foundation blockwork: 100%

3. Borrow Pits
Clearing and top soil removal for gravel fill on the structure

2. Block Moulding
We have produced 43,445 blocks since we started

4. Reinforcement Bar
Cutting and bending for hostel ground beams in progress

Other Pictures

Healthy & Safety

Site Accidents = 1
He is recovering at home.
We do daily tool box meetings where we remind each other on the daily site safety matters.

Theft incidents = 0

Construction Materials

Material quantities and their sources
Cement = 3.8 tones
Sand = 1300 tones
Quarry = 240 tones

FUEL SUPPLIER AND LOCATION
– Nkando ENGEN filling station, Mulanje (7km from Namulenga site)

CEMENT SUPPLIER AND LOCATION
– CPL cement company, Mangochi

QUARRY AND SAND
– Sand: Chisombezi and Namulenga river in Mulanje
– Quarry: Njuli Chiradzulu

###
end update

Progress Report – December 5, 2025

Work progresses as our completion dates nears. […]

Read More

Progress Report – September 30, 2025

Work progresses as our completion dates nears. […]

Read More

Site Plan – October 08, 2025

Work progresses as our completion dates nears. […]

Read More

Progress Report – August 1, 2025

Work progresses as our completion dates nears. […]

Read More

Progress Report – June 20, 2025

Work moving along steadily as we work toward completion. […]

Read More

Progress Report – June 5, 2025

Work continues as we aim to finish by the end of Summer. […]

Read More

Progress Report – May 30, 2025

With the main buildings close to completion, efforts turn toward completing the rectory and playing fields. […]

Read More

Progress Report – May 23, 2025

Work continues as we progress toward our completion date. […]

Read More

Progress Report – May 9, 2025

Work will continue through the summer with a new completion date of August 31, 2025. […]

Read More

Progress Report – April 11, 2025

Progress continues as we work toward a completion date of April 30, 2025. […]

Read More