Updated September 25, 2023
Client: The Archdiocese of Blantyre (TTE/Diocese of Joliet)
Consultant: Team Lift Inc. / Hagios Consulting Engineers
Contractor: Sitbec Ltd.
Proposed Contract Period: 80 weeks
Proposed Commencement Date: January 2, 2023
Proposed Completion Date: July 2, 2024
Time Elapsed: 38 weeks
Pictures of ongoing construction work can be seen below.
Administration Block
Multipurpose Hall
Classrooms (4No)
Pavillions (4 No)
Laboratory (2 No)
Library
Staff Housing (3 No)
Headmaster and Teachers' Housing
Other Works
1. Lavatory
Excavation and cleaning: 100%
Footing: 100%
Foundation blockwork: 100%
3. Borrow Pits
Clearing and top soil removal for gravel fill on the structure
2. Block Moulding
We have produced 43,445 blocks since we started
4. Reinforcement Bar
Cutting and bending for hostel ground beams in progress
Other Pictures
Healthy & Safety
Site Accidents = 1
He is recovering at home.
We do daily tool box meetings where we remind each other on the daily site safety matters.
Theft incidents = 0
Construction Materials
Material quantities and their sources
Cement = 3.8 tones
Sand = 1300 tones
Quarry = 240 tones
FUEL SUPPLIER AND LOCATION
– Nkando ENGEN filling station, Mulanje (7km from Namulenga site)
CEMENT SUPPLIER AND LOCATION
– CPL cement company, Mangochi
QUARRY AND SAND
– Sand: Chisombezi and Namulenga river in Mulanje
– Quarry: Njuli Chiradzulu
###
end update