Updated July 30, 2023

Work continues to progress. Unfortunately, there is currently an economic crisis prevailing in Malawi – fuel shortages. This has resulted in costs/prices of goods and services to skyrocket. This situation has affected the progress of on-going work on site. The contractor is unable to utilize the back-hoe machines to aid in the excavation process, thus resorting to manual digging. That notwithstanding, considerable progress is being made as the morale of the workers on site is very high.

Pictures of ongoing construction work can be seen below.

Administration Block

Setting out: 100% | Excavation: 100% | Sand blinding and leveling: 100% | Underground beam rebars fabrication: 50%

Multipurpose Hall

Setting out: 100% | Excavations: 100% | Leveling: 50%

Western Classrooms

Setting Out: 100% | Excavations: 75%
Leveling: 50%

Western Laboratory (1No)

Setting: 100% | Excavations: 65%

Western Pavilions (2No)

Setting: 100% | Excavation: 70%
Leveling: 50%

Eastern Classrooms (2 No)

Setting Out: 100% | Excavations: 70%
Leveling: 45%

Eastern Laboratory (1 No)

Setting Out: 100% | Excavation & cleaning: 45%

2 Eastern Pavilions

Setting Out: 95%
Excavations: 50%

Library

Setting Out: 100%
Excavation: 60%

Western Hostels (3 No)

Setting Out: 45%

Staff Housing

Setting Out: 80%

Headmaster and Teachers’ Housing

Setting Out: 100%
Excavation & Cleaning: 30%

Structures being set out now:

  • Eastern hostels (3No)
  • The clock tower (location not yet identified as of last site meeting.)

###
end update

Progress Report – April 5, 2024

Work continues with progress being made on spring targets. […]

Read More

Progress Report – March 22, 2024

March tasks on target; new targets set for April. […]

Read More

Progress Report – February 23, 2024

Work continues with goals set forth for March 2024. […]

Read More

Progress Report – January 26, 2024

Superstructure block work in progress for most of project. […]

Read More

Progress Report – December 1, 2023

We are racing against time to complete all substructure work before the Christmas close down. […]

Read More

Progress Report – September 21, 2023

At 38 weeks in, we are making good progress. […]

Read More

Construction Begins

The much-awaited construction of the Our Lady of Namulenga High School, has begun in earnest. […]

Read More